 "dataset": "grid-rules",
 "version": "1.4.0",
 "generated_on": "2026-10-31",
 "licence": "CC BY 4.0 for ComputeFinder-owned summaries, labels and compilation rights only, except where a record supplies a specific adaptation licence. Third-party material retains its source terms.",
 "licence_url": "https://creativecommons.org/licenses/by/4.0/",
 "licence_scope": "Only copyright and database rights controlled by ComputeFinder in its original contributions. No third-party rights are granted. Source reuse terms have not been comprehensively cleared; consult each linked source. Private submissions, contact details, code and branding are excluded.",
 "source_terms_status": "Not comprehensively cleared; check linked sources before reusing third-party material.",
 "attribution": "Compiled by ComputeFinder (https://computefinder.net). Original contributions licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/), except adaptations carrying a record-specific licence. Give appropriate credit, retain licence and source notices, and indicate changes when sharing. Each record links its primary source; retain any attribution required by that source. Material is provided as-is without warranties.",
 "note": "No prices are included. Missing values are null or absent, never zero.",
 "records": [
  {
   "operator": "ERCOT",
   "region": "Texas, United States",
   "topic": "Large load batch study process",
   "summary_own_words": "ERCOT is building a Batch Study process that groups large loads meeting strict requirements into single studies, to give consistent and system-wide results. The working group page lists meetings from December 2025 (workshops from February 2026) and weekly Batch Zero readiness meetings up to July 2026, with nothing scheduled for September.",
   "source_url": "https://www.ercot.com/committees/tac/llwg",
   "as_of": "2026-10-03",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "operator": "AEMO",
   "region": "National Electricity Market, Australia",
   "topic": "Data centre connections and demand outlook",
   "summary_own_words": "AEMO calls data centres among the fastest growing sources of demand and says large connections are targeting about two years from application to energisation. Its page counts 11 large transmission pipeline projects above 5MW, and it expects the share of national electricity use to rise by 2030 and 2050. It has also asked the AEMC, through a rule change request, for a clearer and more consistent framework for how large loads connect and perform.",
   "source_url": "https://www.aemo.com.au/Newsroom/News-Updates/Digital-demand-surge",
   "as_of": "2026-06-01",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "operator": "AEMO",
   "region": "National Electricity Market, Australia",
   "topic": "Data centre forecast method and project completion rate",
   "summary_own_words": "AEMO's 2026 forecast overview combines developer project data with economic modelling. It notes that many announced projects have not been built historically, which is why it does not treat the full list of developing sites as expected demand. The overview projects operational consumption from data centres roughly tripling by FY30 under its Step Change scenario.",
   "source_url": "https://www.aemo.com.au/-/media/files/electricity/nem/planning_and_forecasting/nem_esoo/2026/2026-esoo-data-centre-forecasting-overview.pdf",
   "as_of": "2026-08-25",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "operator": "AEMC (for Australian ministers)",
   "region": "Australia",
   "topic": "Large load register and cost recovery",
   "summary_own_words": "The energy minister's rule change requests propose a public register of prospective and existing large loads of 5MW or more, prudential arrangements to guard against stranded network assets, and guidance on transmission connection pricing. The AEMC opened consultation on them on 24 September 2026.",
   "source_url": "https://www.aemc.gov.au/sites/default/files/2026-08/ERC0448%20and%20ERC0456%20-%20Rule%20change%20request.pdf",
   "as_of": "2026-07-01",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "operator": "EirGrid",
   "region": "Ireland",
   "topic": "Data centre connection offer process (CRU policy implementation)",
   "summary_own_words": "Version 3 of EirGrid's process applies to data centres of 1MVA or more seeking transmission connection. Applicants must show dispatchable on-site or nearby generation matched to import capacity, plus new Irish renewable supply for at least 80% of annual demand over a six-year glide path. Applications in constrained network areas cannot proceed, and EirGrid estimates about 7.5 to 18 months to process complete applications depending on generation status.",
   "source_url": "https://cms.eirgrid.ie/sites/default/files/publications/Data-Centre-Connection-Offer-Process-and-Policy-V3-May-2026.pdf",
   "as_of": "2026-05-20",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "operator": "FERC",
   "region": "United States (PJM, MISO, SPP, CAISO, ISO-NE, NYISO)",
   "topic": "Large load show cause orders",
   "summary_own_words": "On 18 June 2026 FERC ordered six grid operators to justify or reform their tariffs for large loads, covering transmission service procedures, cost transparency, co-located generation, flexible transmission service and generation serving adjacent loads. Operators had 60 days to respond and 30 days to report on resource adequacy.",
   "source_url": "https://www.ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration",
   "as_of": "2026-06-18",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "operator": "SPP",
   "region": "Central United States",
   "topic": "High Impact Large Load integration",
   "summary_own_words": "SPP offers a Conditional High Impact Large Load service with expedited access and possible curtailment during system stress, and a generation assessment that studies loads and supporting on-site generation in parallel. It targets interconnection agreements within 90 days and is holding stakeholder question sessions from May to October 2026.",
   "source_url": "https://spp.org/markets-operations/high-impact-large-load-hill-integration/",
   "as_of": "2026-10-03",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "operator": "PJM",
   "region": "Mid-Atlantic and Midwest, United States",
   "topic": "Large load ride-through reliability proposal",
   "summary_own_words": "PJM wants large computational loads to ride through grid disturbances rather than disconnect, after a July 2026 event in northern Virginia when close to 4,000MW of data centre load dropped. It intends to file proposals with FERC in November 2026 and says MISO, ERCOT and NERC are developing similar standards.",
   "source_url": "https://insidelines.pjm.com/reliability-standards-to-manage-large-load-disconnection-events-proposed-by-pjm/",
   "as_of": "2026-09-10",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "operator": "NESO",
   "region": "Great Britain",
   "topic": "Connections reform Gate 2 offer timetable",
   "summary_own_words": "NESO's timeline shows Gate 2 offers for transmission and large embedded projects issued in two phases, mid-May to mid-September 2026 and early September 2026 to mid-January 2027, and distribution offers in two phases, early July to mid-November 2026 and mid-October 2026 to mid-March 2027. The page does not break out data centres or other demand, so it is context for queue timing only.",
   "source_url": "https://www.neso.energy/industry-information/connections-reform/connections-reform-timeline",
   "as_of": "2026-10-03",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "operator": "Lawrence Berkeley National Laboratory",
   "region": "United States",
   "topic": "Queued Up 2026 edition, generation and storage queues",
   "summary_own_words": "The 2026 edition reports the active generation and storage queue fell about 10% year on year by end 2025, with gas capacity rising sharply and a median of over five years from request to operation for projects built in 2025. It states that load interconnection requests, including data centres, are not in the dataset, so it should not be read as a measure of data centre queues.",
   "source_url": "https://emp.lbl.gov/publications/queued-2026-edition-characteristics",
   "as_of": "2026-05-01",
   "page_url": "https://computefinder.net/grid-rules"
  },
  {
   "slug": "tennet-nl-tdtr-2026-operationalisation",
   "operator": "TenneT (Netherlands); ACM decision",
   "region": "Netherlands",
   "jurisdiction": "NL",
   "topic": "Historical TDTR notification timing and release time granularity",
   "summary_own_words": "ACM amended the Dutch TDTR code provisions in its decision of 23 April 2026. The amendment changes notification timing and the time granularity used to release capacity.",
   "source_url": "https://zoek.officielebekendmakingen.nl/stcrt-2026-17010.html",
   "as_of": "2026-04-23",
   "evidence_kind": "regulator_code_amendment",
   "source_publication": "2026-05-07",
   "source_updated_on": null,
   "event_date": "2026-04-23",
   "retrieved_at": null,
   "reviewed_at": "2026-10-31T23:14:15.906Z",
   "source_version": null,
   "checked_on": "2026-10-31",
   "source_notice": "Only minimal independently worded attributed facts and ordinary unframed links are used. No source narrative, table, chart, marks, personal contacts, dataset or full document is copied. No open licence or recurring-monitoring grant is asserted.",
   "reuse_terms": null,
   "rights_notice_url": "https://www.acm.nl/nl/over-deze-site",
   "instrument": "Staatscourant 2026, 17010; ACM/UIT/671095; ACM/25/199016",
   "instrument_version": "decision of 23 April 2026",
   "effective_date": "2026-05-08",
   "effective_date_basis": "Calendar consequence of Article II: day after the Gazette issue dated 7 May 2026; separately identified inference, not a retrieval clock.",
   "applicability": "Dutch Systeemcode elektriciteit 2026 TDTR amendment only. Not TenneT Germany, a site-specific offer, or guaranteed unrestricted transport.",
   "threshold": null,
   "transition": "The amendment supplies its own commencement rule. Consolidated current code and later amendments were not reviewed.",
   "limits": "Consolidated TDTR product provisions were not reviewed in this narrow amendment account. No congestion-area headroom or project eligibility is established.",
   "page_url": "https://computefinder.net/grid-rules"
  }
 ]
}