 "schema_version": "1.0",
 "title": "ComputeFinder connected project evidence: initial selected cohort",
 "scope": "Selected existing published observations and original editorial interpretation. This is not a physical-facility census, a current status check or a complete change history.",
 "licence": "CC BY 4.0 applies to ComputeFinder-owned compilation and original interpretation only. Third-party source material and source-use conditions retain their own scope.",
 "licence_url": "https://creativecommons.org/licenses/by/4.0/",
 "unknown_states": {
  "not_researched": "Not researched in this file",
  "not_established": "Not established by the evidence inspected",
  "conflict": "Conflicting evidence",
  "not_applicable": "Not applicable to this question"
 },
 "entities": [
  {
   "id": "gromstul-project-context",
   "type": "project_evidence_context",
   "name": "Gromstul, Skien",
   "canonical_path": "/data-centres/skien-gromstul-telemark"
  },
  {
   "id": "gromstul-building-1-and-2",
   "type": "distinct_building_context",
   "name": "Building 1 and proposed Building 2",
   "identity_limit": "Two described building scopes, not one verified physical-facility identity."
  },
  {
   "id": "gromstul-electrical-case",
   "type": "permission_case",
   "name": "NVE case 202607246",
   "source_url": "https://www.nve.no/konsesjon/konsesjonssaker/konsesjonssak?id=26039&type=A-1"
  },
  {
   "id": "gromstul-permitted-line-scopes",
   "type": "permission_scope",
   "name": "Building 1 to Building 2 and Gromstul switch station to data-centre transformer station 132 kV line scopes",
   "identity_limit": "Named permission scopes only; no construction, energisation or commissioning is established."
  },
  {
   "id": "ws-computing-permission-recipient",
   "type": "organisation",
   "name": "WS Computing AS",
   "identity_limit": "Named electrical-permission recipient here, not a new verification of owner, operator or end user."
  },
  {
   "id": "middenmeer-project-context",
   "type": "project_evidence_context",
   "name": "Microsoft evidence at Middenmeer",
   "canonical_path": "/data-centres/microsoft-middenmeer"
  },
  {
   "id": "middenmeer-historical-record",
   "type": "historical_site_record",
   "name": "Existing Wieringermeer reference mapped to Middenmeer",
   "canonical_path": "/data-centres/microsoft-middenmeer"
  },
  {
   "id": "middenmeer-ams-e-b1",
   "type": "proposed_project_phase",
   "name": "AMS-E, Deelgebied B1, Westlanderweg 50",
   "identity_limit": "No verified physical-campus or phase association with the historical record, Westlanderweg 150, AMS13/14, AMS15/40 or Campus West."
  },
  {
   "id": "microsoft-netherlands-notice-applicant",
   "type": "organisation",
   "name": "Microsoft Datacenters Netherlands B.V.",
   "identity_limit": "Named proposed expansion in the reviewed notice, not a new verification of campus ownership."
  },
  {
   "id": "hepokorpi-project-context",
   "type": "project_evidence_context",
   "name": "Hepokorpi, Espoo",
   "canonical_path": "/data-centres/microsoft-hepokorpi-espoo"
  },
  {
   "id": "hepokorpi-phase-3",
   "type": "project_phase",
   "name": "Hepokorpi phase 3",
   "identity_limit": "The permit concerns this phase; it does not set the current stage of every phase."
  },
  {
   "id": "hepokorpi-programme-context",
   "type": "multi_location_programme_context",
   "name": "Microsoft Finnish construction programme",
   "identity_limit": "Programme reporting is not a single-site delivery observation or a capacity total."
  }
 ],
 "observations": [
  {
   "id": "gromstul-building-context",
   "subject": "gromstul-building-1-and-2",
   "text": "A December 2025 noise report says Building 1 is under construction and Building 2, a planned southern extension, would add server halls, 70 cooling units and 46 backup diesel generators.",
   "scope": "Historical Building 1 construction and proposed Building 2 context, not a new campus-wide stage observation.",
   "evidence_kind": "historical published record",
   "source_url": "https://www.statsforvalteren.no/siteassets/fm-vestfold-og-telemark/miljo-og-klima/forurensning/dokumenter/2026/horinger/gromstul/vedlegg-10-stoyutredning.pdf",
   "source_label": "December 2025 noise report, as retained in the existing record",
   "source_publication_date": null,
   "source_updated_on": null,
   "event_date": null,
   "stage_observation_date": "2025-12-12",
   "checked_on": "2026-10-02",
   "independently_reviewed_at": null,
   "retrieved_at": null,
   "provenance": {
    "record_path": "/data-centres/skien-gromstul-telemark",
    "record_source": "src/content/sites-europe.js",
    "field": "facts[0]",
    "review_scope": "Reuses the published record. No fresh source retrieval or whole-record revalidation in this edition; an exact independent review timestamp is not stored in this record."
   },
   "source_notice": {
    "licence": "Existing source conditions retained; no new source-content licence",
    "scope": "Selected existing attributed fact and ordinary original link only. Third-party source material retains its terms. This evidence file creates no blanket reuse or recurring-monitoring permission."
   }
  },
  {
   "id": "gromstul-electrical-licence",
   "subject": "gromstul-electrical-case",
   "text": "NVE lists the Gromstul electrical-installation case as licence granted, dated 28 August 2026, and says permission was given to WS Computing AS for electrical installations linked to the data centre in Skien.",
   "scope": "NVE case status for electrical installations linked to the project; not all campus consents or energisation.",
   "evidence_kind": "reviewed source supplement",
   "source_url": "https://www.nve.no/konsesjon/konsesjonssaker/konsesjonssak?id=26039&type=A-1",
   "source_label": "NVE: Gromstul electrical-installation case",
   "source_publication_date": null,
   "source_updated_on": null,
   "event_date": "2026-08-28",
   "event_date_scope": "Date listed against this licence-granted case status, not a new campus-stage observation",
   "stage_observation_date": null,
   "checked_on": "2026-10-17",
   "independently_reviewed_at": "2026-10-17T17:31:59Z",
   "retrieved_at": null,
   "observed_at_upper_bound": "2026-10-17T17:30:26Z",
   "parsed_evidence": {
    "sha256": "8c81c4753e636ddbe4fd11e9a0813489cb41f880159851cefb4bddd749a20920",
    "kind": "Selected parsed case lines transcribed from a connected-tool response, not origin HTML or a complete body hash"
   },
   "raw_body_sha256": null,
   "raw_body_bytes": null,
   "provenance": {
    "record_path": "/data-centres/skien-gromstul-telemark",
    "record_source": "src/content/decision-evidence.js",
    "field": "skien-gromstul-telemark.claims[0]",
    "review_scope": "The existing exact-use independent review, not a new check in this edition."
   },
   "limitations": "The inspected evidence is the case HTML, not the underlying decision PDF or attachments. Electrical-installation permission does not establish all campus consents, legal finality, a current comment or appeal window, completion, commissioning, current operation, capacity or available compute. WS Computing AS is the named permission recipient, not newly verified campus owner, operator or end user. Earlier campus facts, stage, capacity and source dates are unchanged; no building or phase is split or merged.",
   "source_notice": {
    "publisher": "NVE and relevant underlying rightsholders",
    "licence": "Source copyright retained; exact basic-fact use assessed only",
    "licence_url": null,
    "scope": "Two minimal attributed basic case facts and ordinary unframed case link only. No source narrative, quotations, attachments, maps, drawings, images, contacts, tables or datasets reproduced or adapted. No open licence, public-domain status, endorsement, blanket domain clearance or recurring-monitoring grant. The inspected NVE open-data notice applies NLOD to api.nve.no data, not automatically this case HTML or attachments; no API data was acquired. No applicable express restriction was visible in the complete case and inspected notices; this is not proof that no broader terms exist. Reassess newly evidenced applicable conditions without a paraphrase workaround."
   }
  },
  {
   "id": "gromstul-electrical-line-scope",
   "subject": "gromstul-electrical-case",
   "text": "NVE lists case 202607246 as licence granted, dated 28 August 2026. A separate page for the same case identifies two 132 kV line scopes in its title: Building 1 to Building 2, and Gromstul switch station to the data-centre transformer station.",
   "scope": "The title identifies two permitted 132 kV line spans within the same case; not construction, energisation or commissioning.",
   "evidence_kind": "reviewed source supplement",
   "source_url": "https://www.nve.no/konsesjon/konsesjonssaker/konsesjonssak?id=26255&type=A-1",
   "source_label": "NVE: Gromstul permitted 132 kV line scopes",
   "source_publication_date": null,
   "source_updated_on": null,
   "event_date": "2026-08-28",
   "event_date_scope": "Date listed with the licence-granted case status, not source publication, construction, energisation or commissioning",
   "stage_observation_date": null,
   "checked_on": "2026-10-25",
   "independently_reviewed_at": "2026-10-25T16:32:51.701Z",
   "retrieved_at": null,
   "observed_at_upper_bound": "2026-10-25T16:32:38.089Z",
   "parsed_evidence": {
    "sha256": "4a754b27a0a1367978d7e1e823cbaf65267f125650b608fdbc4594fb8c1b8993",
    "kind": "Selected parsed case title and fields, not origin HTML or a complete body hash"
   },
   "raw_body_sha256": null,
   "raw_body_bytes": null,
   "provenance": {
    "record_path": "/data-centres/skien-gromstul-telemark",
    "record_source": "src/content/decision-evidence.js",
    "field": "skien-gromstul-telemark-lines.claims[0]",
    "review_scope": "The existing exact-use independent review, not a new check in this edition."
   },
   "limitations": "This separate page is another scope view of case 202607246, not a distinct project event. Its title identifies permitted line spans; it does not establish that either link was built, energised or commissioned, or that every electrical work or consent is complete. It does not establish current operation, capacity or available compute. Existing project stage, capacity, construction, consent and source clocks remain unchanged.",
   "source_notice": {
    "publisher": "NVE and relevant underlying rightsholders",
    "licence": "Source copyright retained; exact basic-fact use assessed only",
    "licence_url": null,
    "scope": "One minimal attributed case/title fact and ordinary unframed case link only. No source narrative, quotations, attachments, maps, drawings, images, contacts, tables or datasets reproduced or adapted. No open licence, public-domain status, endorsement, blanket domain clearance or recurring-monitoring grant. The earlier inspected NVE open-data notice applies NLOD to api.nve.no data, not automatically this case HTML or attachments. Existing source-use review was read but is not treated as blanket permission; the exact candidate was independently reviewed."
   }
  },
  {
   "id": "middenmeer-historical-site",
   "subject": "middenmeer-historical-record",
   "text": "The Dutch parliament's 23 June 2022 page lists an existing Microsoft hyperscale data centre in Wieringermeer; this record maps it to Middenmeer.",
   "scope": "The parliamentary reference names Wieringermeer; the existing catalogue maps it to Middenmeer. This is historical evidence, not a current operating check.",
   "evidence_kind": "historical published record",
   "source_url": "https://www.tweedekamer.nl/debat_en_vergadering/uitgelicht/datacenters-nederland",
   "source_label": "Dutch parliament: data centres in the Netherlands",
   "source_publication_date": "2022-06-23",
   "source_updated_on": null,
   "event_date": null,
   "stage_observation_date": "2022-06-23",
   "checked_on": "2026-10-02",
   "independently_reviewed_at": null,
   "retrieved_at": null,
   "provenance": {
    "record_path": "/data-centres/microsoft-middenmeer",
    "record_source": "src/content/sites-europe.js",
    "field": "facts[0]",
    "review_scope": "Reuses the published record. No fresh source retrieval or whole-record revalidation in this edition; an exact independent review timestamp is not stored in this record."
   },
   "source_notice": {
    "licence": "Existing source conditions retained; no new source-content licence",
    "scope": "Selected existing attributed fact and ordinary original link only. Third-party source material retains its terms. This evidence file creates no blanket reuse or recurring-monitoring permission."
   }
  },
  {
   "id": "middenmeer-mer-notice",
   "subject": "middenmeer-ams-e-b1",
   "text": "A Noord-Holland notice published on 30 December 2025 records a MER preparation notification for Microsoft Datacenters Netherlands B.V.'s proposed AMS-E, Deelgebied B1 expansion at Westlanderweg 50, Middenmeer, case OD2025-0043382.",
   "scope": "The proposed AMS-E, Deelgebied B1 expansion at Westlanderweg 50 only. Its physical association with the older record is not established.",
   "evidence_kind": "reviewed source supplement",
   "source_url": "https://zoek.officielebekendmakingen.nl/prb-2025-21956.html",
   "source_label": "Noord-Holland: AMS-E, Deelgebied B1 MER-intent notice",
   "source_publication_date": "2025-12-30",
   "source_updated_on": null,
   "event_date": null,
   "event_date_scope": null,
   "stage_observation_date": null,
   "checked_on": "2026-10-17",
   "independently_reviewed_at": "2026-10-17T18:36:44Z",
   "retrieved_at": null,
   "observed_at_upper_bound": "2026-10-17T18:35:19Z",
   "parsed_evidence": {
    "sha256": "d9b76d25083f033dd6800d4e6838066ba41c8a0f597d8ab74bf4acb6098826c4",
    "kind": "Selected parsed notice lines transcribed from a connected-tool response, not origin bytes, raw HTML or a complete body hash"
   },
   "raw_body_sha256": null,
   "raw_body_bytes": null,
   "provenance": {
    "record_path": "/data-centres/microsoft-middenmeer",
    "record_source": "src/content/decision-evidence.js",
    "field": "microsoft-middenmeer.claims[0]",
    "review_scope": "The existing exact-use independent review, not a new check in this edition."
   },
   "limitations": "This supplement is locality/operator discovery context beside the older Microsoft Middenmeer record, not a verified physical-campus or phase association. AMS-E, Deelgebied B1 and Westlanderweg 50 are not matched to Westlanderweg 150, AMS13/14, AMS15/40 or Campus West in the separate coordination decision. The underlying case documents, NRD, PDFs, applications and later decisions were not inspected. This historic notice does not establish current permitting, legal finality, a current comment or appeal window, construction, operation, capacity or available compute. Earlier facility facts, stages, planning and source dates remain unchanged; no building or phase is split or merged.",
   "source_notice": {
    "publisher": "Province of Noord-Holland and relevant underlying rightsholders",
    "licence": "Source copyright retained; exact basic-fact use assessed only",
    "licence_url": null,
    "scope": "Two minimal attributed basic notice facts and ordinary unframed original link only, not source narrative translation, adaptation or legal advice. No quotations, applicant documents, attachments, maps, drawings, images, contacts, tables or datasets reproduced or adapted. No open licence, public-domain status, endorsement, blanket domain clearance or recurring-monitoring grant. The inspected KOOP CC0 notice is limited to its own website, not this provincial notice or third-party attachments. No express restriction on the bounded basic-fact/link use was visible in the inspected notice HTML; inaccessible Overheid help/reuse conditions remain uninspected, not permission inferred from absence. Reassess newly evidenced applicable conditions without a paraphrase workaround."
   }
  },
  {
   "id": "middenmeer-mer-boundary",
   "subject": "middenmeer-ams-e-b1",
   "text": "The notice states that the MER procedure does not itself decide the environmental permit; that decision follows completion of the MER and submission of a permit application.",
   "scope": "The notice describes the distinction between the MER procedure and a later permit decision; it is not a current legal-status assessment.",
   "evidence_kind": "reviewed source supplement",
   "source_url": "https://zoek.officielebekendmakingen.nl/prb-2025-21956.html",
   "source_label": "Noord-Holland: AMS-E, Deelgebied B1 MER-intent notice",
   "source_publication_date": "2025-12-30",
   "source_updated_on": null,
   "event_date": null,
   "event_date_scope": null,
   "stage_observation_date": null,
   "checked_on": "2026-10-17",
   "independently_reviewed_at": "2026-10-17T18:36:44Z",
   "retrieved_at": null,
   "observed_at_upper_bound": "2026-10-17T18:35:19Z",
   "parsed_evidence": {
    "sha256": "d9b76d25083f033dd6800d4e6838066ba41c8a0f597d8ab74bf4acb6098826c4",
    "kind": "Selected parsed notice lines transcribed from a connected-tool response, not origin bytes, raw HTML or a complete body hash"
   },
   "raw_body_sha256": null,
   "raw_body_bytes": null,
   "provenance": {
    "record_path": "/data-centres/microsoft-middenmeer",
    "record_source": "src/content/decision-evidence.js",
    "field": "microsoft-middenmeer.claims[1]",
    "review_scope": "The existing exact-use independent review, not a new check in this edition."
   },
   "limitations": "This supplement is locality/operator discovery context beside the older Microsoft Middenmeer record, not a verified physical-campus or phase association. AMS-E, Deelgebied B1 and Westlanderweg 50 are not matched to Westlanderweg 150, AMS13/14, AMS15/40 or Campus West in the separate coordination decision. The underlying case documents, NRD, PDFs, applications and later decisions were not inspected. This historic notice does not establish current permitting, legal finality, a current comment or appeal window, construction, operation, capacity or available compute. Earlier facility facts, stages, planning and source dates remain unchanged; no building or phase is split or merged.",
   "source_notice": {
    "publisher": "Province of Noord-Holland and relevant underlying rightsholders",
    "licence": "Source copyright retained; exact basic-fact use assessed only",
    "licence_url": null,
    "scope": "Two minimal attributed basic notice facts and ordinary unframed original link only, not source narrative translation, adaptation or legal advice. No quotations, applicant documents, attachments, maps, drawings, images, contacts, tables or datasets reproduced or adapted. No open licence, public-domain status, endorsement, blanket domain clearance or recurring-monitoring grant. The inspected KOOP CC0 notice is limited to its own website, not this provincial notice or third-party attachments. No express restriction on the bounded basic-fact/link use was visible in the inspected notice HTML; inaccessible Overheid help/reuse conditions remain uninspected, not permission inferred from absence. Reassess newly evidenced applicable conditions without a paraphrase workaround."
   }
  },
  {
   "id": "hepokorpi-phase-3-permit",
   "subject": "hepokorpi-phase-3",
   "text": "On 11 June 2026 the Espoo environment and building board approved a phase 3 building permit for Microsoft 3465 Finland Oy and allowed work to begin before the permit is final.",
   "scope": "The 11 June 2026 phase 3 building-permit account. It does not establish phase 3 construction, legal finality or current operation.",
   "evidence_kind": "historical published record",
   "source_url": "https://www.sttinfo.fi/tiedote/72129950/ymparisto-ja-rakennuslautakunta-hepokorven-datakeskuksen-kolmannelle-vaiheelle-rakennuslupa?lang=fi",
   "source_label": "City of Espoo announcement via STT Info",
   "source_publication_date": "2026-06-12",
   "source_updated_on": null,
   "event_date": "2026-06-11",
   "stage_observation_date": null,
   "checked_on": "2026-10-02",
   "independently_reviewed_at": null,
   "retrieved_at": null,
   "provenance": {
    "record_path": "/data-centres/microsoft-hepokorpi-espoo",
    "record_source": "src/content/sites-europe.js",
    "field": "facts[0]",
    "review_scope": "Reuses the published record. No fresh source retrieval or whole-record revalidation in this edition; an exact independent review timestamp is not stored in this record."
   },
   "source_notice": {
    "licence": "Existing source conditions retained; no new source-content licence",
    "scope": "Selected existing attributed fact and ordinary original link only. Third-party source material retains its terms. This evidence file creates no blanket reuse or recurring-monitoring permission."
   }
  },
  {
   "id": "hepokorpi-construction-programme",
   "subject": "hepokorpi-programme-context",
   "text": "Microsoft said in April 2026 that first-phase construction began in late 2024 and should finish around the turn of 2026 to 2027, with second-phase work starting in 2026 at Espoo, Kirkkonummi and Vihti.",
   "scope": "Microsoft programme-level construction reporting covering Espoo, Kirkkonummi and Vihti. A reported target is not completed delivery at Hepokorpi.",
   "evidence_kind": "historical published record",
   "source_url": "https://news.microsoft.com/source/emea/2026/04/microsoft-kaynnistaa-paakaupunkiseudun-datakeskusalueen-toisen-vaiheen-rakentamisen/?lang=fi",
   "source_label": "Microsoft: April 2026 Finnish construction programme account",
   "source_publication_date": null,
   "source_updated_on": null,
   "event_date": null,
   "stage_observation_date": null,
   "checked_on": "2026-10-02",
   "independently_reviewed_at": null,
   "retrieved_at": null,
   "provenance": {
    "record_path": "/data-centres/microsoft-hepokorpi-espoo",
    "record_source": "src/content/sites-europe.js",
    "field": "facts[2]",
    "review_scope": "Reuses the published record. No fresh source retrieval or whole-record revalidation in this edition; an exact independent review timestamp is not stored in this record."
   },
   "source_notice": {
    "licence": "Existing source conditions retained; no new source-content licence",
    "scope": "Selected existing attributed fact and ordinary original link only. Third-party source material retains its terms. This evidence file creates no blanket reuse or recurring-monitoring permission."
   }
  }
 ],
 "relationships": [
  {
   "id": "gromstul-electrical-context",
   "from": "gromstul-project-context",
   "relation": "has scoped electrical case",
   "to": "gromstul-electrical-case",
   "status": "supported within stated scope",
   "observation_id": "gromstul-electrical-licence",
   "source_url": "https://www.nve.no/konsesjon/konsesjonssaker/konsesjonssak?id=26039&type=A-1",
   "source_publication_date": null,
   "event_date": "2026-08-28",
   "stage_observation_date": null,
   "checked_on": "2026-10-17",
   "scope": "NVE case status for electrical installations linked to the project; not all campus consents or energisation."
  },
  {
   "id": "gromstul-permission-recipient",
   "from": "gromstul-electrical-case",
   "relation": "names permission recipient",
   "to": "ws-computing-permission-recipient",
   "status": "supported within stated scope",
   "observation_id": "gromstul-electrical-licence",
   "source_url": "https://www.nve.no/konsesjon/konsesjonssaker/konsesjonssak?id=26039&type=A-1",
   "source_publication_date": null,
   "event_date": "2026-08-28",
   "stage_observation_date": null,
   "checked_on": "2026-10-17",
   "scope": "NVE case status for electrical installations linked to the project; not all campus consents or energisation."
  },
  {
   "id": "gromstul-electrical-line-scope",
   "from": "gromstul-electrical-case",
   "relation": "lists two permitted 132 kV line scopes",
   "to": "gromstul-permitted-line-scopes",
   "status": "supported within stated scope",
   "observation_id": "gromstul-electrical-line-scope",
   "source_url": "https://www.nve.no/konsesjon/konsesjonssaker/konsesjonssak?id=26255&type=A-1",
   "source_publication_date": null,
   "event_date": "2026-08-28",
   "stage_observation_date": null,
   "checked_on": "2026-10-25",
   "scope": "The title identifies two permitted 132 kV line spans within the same case; not construction, energisation or commissioning."
  },
  {
   "id": "gromstul-building-context",
   "from": "gromstul-project-context",
   "relation": "has historical building context",
   "to": "gromstul-building-1-and-2",
   "status": "supported within stated scope",
   "observation_id": "gromstul-building-context",
   "source_url": "https://www.statsforvalteren.no/siteassets/fm-vestfold-og-telemark/miljo-og-klima/forurensning/dokumenter/2026/horinger/gromstul/vedlegg-10-stoyutredning.pdf",
   "source_publication_date": null,
   "event_date": null,
   "stage_observation_date": "2025-12-12",
   "checked_on": "2026-10-02",
   "scope": "Historical Building 1 construction and proposed Building 2 context, not a new campus-wide stage observation."
  },
  {
   "id": "middenmeer-locality-context",
   "from": "middenmeer-historical-record",
   "relation": "shares locality and operator discovery context only",
   "to": "middenmeer-ams-e-b1",
   "status": "physical association not established",
   "observation_id": "middenmeer-mer-notice",
   "source_url": "https://zoek.officielebekendmakingen.nl/prb-2025-21956.html",
   "source_publication_date": "2025-12-30",
   "event_date": null,
   "stage_observation_date": null,
   "checked_on": "2026-10-17",
   "scope": "The proposed AMS-E, Deelgebied B1 expansion at Westlanderweg 50 only. Its physical association with the older record is not established."
  },
  {
   "id": "middenmeer-notice-applicant",
   "from": "middenmeer-ams-e-b1",
   "relation": "names proposed expansion applicant",
   "to": "microsoft-netherlands-notice-applicant",
   "status": "supported within stated scope",
   "observation_id": "middenmeer-mer-notice",
   "source_url": "https://zoek.officielebekendmakingen.nl/prb-2025-21956.html",
   "source_publication_date": "2025-12-30",
   "event_date": null,
   "stage_observation_date": null,
   "checked_on": "2026-10-17",
   "scope": "The proposed AMS-E, Deelgebied B1 expansion at Westlanderweg 50 only. Its physical association with the older record is not established."
  },
  {
   "id": "hepokorpi-phase-context",
   "from": "hepokorpi-project-context",
   "relation": "has scoped phase 3 permit account",
   "to": "hepokorpi-phase-3",
   "status": "supported within stated scope",
   "observation_id": "hepokorpi-phase-3-permit",
   "source_url": "https://www.sttinfo.fi/tiedote/72129950/ymparisto-ja-rakennuslautakunta-hepokorven-datakeskuksen-kolmannelle-vaiheelle-rakennuslupa?lang=fi",
   "source_publication_date": "2026-06-12",
   "event_date": "2026-06-11",
   "stage_observation_date": null,
   "checked_on": "2026-10-02",
   "scope": "The 11 June 2026 phase 3 building-permit account. It does not establish phase 3 construction, legal finality or current operation."
  },
  {
   "id": "hepokorpi-programme-context",
   "from": "hepokorpi-project-context",
   "relation": "has wider programme reporting",
   "to": "hepokorpi-programme-context",
   "status": "supported within stated scope",
   "observation_id": "hepokorpi-construction-programme",
   "source_url": "https://news.microsoft.com/source/emea/2026/04/microsoft-kaynnistaa-paakaupunkiseudun-datakeskusalueen-toisen-vaiheen-rakentamisen/?lang=fi",
   "source_publication_date": null,
   "event_date": null,
   "stage_observation_date": null,
   "checked_on": "2026-10-02",
   "scope": "Microsoft programme-level construction reporting covering Espoo, Kirkkonummi and Vihti. A reported target is not completed delivery at Hepokorpi."
  }
 ],
 "projects": [
  {
   "slug": "gromstul",
   "path": "/projects/gromstul",
   "title": "Gromstul: construction and electrical permission have different scopes",
   "canonical_record_path": "/data-centres/skien-gromstul-telemark",
   "country": "NO",
   "locality": "Gromstul, Skien, Telemark",
   "entity_id": "gromstul-project-context",
   "catalogue_stage": {
    "value": "under_construction",
    "as_of": "2025-12-12",
    "source_url": "https://www.statsforvalteren.no/siteassets/fm-vestfold-og-telemark/miljo-og-klima/forurensning/dokumenter/2026/horinger/gromstul/vedlegg-10-stoyutredning.pdf",
    "checked_on": "2026-10-02",
    "scope": "Retained historical catalogue label, not a fresh whole-project status check or a delivery-confidence score."
   },
   "change_history": {
    "status": "not_established",
    "material_change_detected_at": null,
    "previous_observation_id": null,
    "explanation": "This first connected evidence file assembles existing published observations. It does not establish a newly detected project change or a complete change history. A later source date alone is not evidence that the whole project advanced."
   },
   "summary": "A historical construction account and a later electrical-installation licence establish different parts of the evidence picture. Neither establishes usable compute today.",
   "scope": "The Gromstul project context includes historical Building 1 and proposed Building 2 reporting, beside a separately scoped NVE electrical case. These are not interchangeable campus-wide stages.",
   "supported_position": "The existing record retains a Building 1 construction observation from December 2025. The separately reviewed NVE case lists electrical-installation permission dated 28 August 2026; another page for that case names two permitted 132 kV line spans. These listings do not update the old building-stage observation or establish completed electrical work.",
   "observation_ids": [
    "gromstul-building-context",
    "gromstul-electrical-licence",
    "gromstul-electrical-line-scope"
   ],
   "briefing_observation_ids": [
    "gromstul-electrical-licence",
    "gromstul-electrical-line-scope"
   ],
   "dependency": "The NVE listing identifies two permitted 132 kV line scopes. Seek separately dated evidence for their construction and energisation, the relevant building, remaining consents and commissioning.",
   "local_implications": "The existing record links zoning and emissions evidence. Their presence does not establish that concerns are resolved, participation is open or benefits have been delivered.",
   "gaps": [
    {
     "question": "Current construction, commissioning and usable capacity",
     "state": "not_established",
     "consequence": "The historical construction observation and electrical permission cannot answer whether compute can be used now."
    },
    {
     "question": "Current participation route and deadline",
     "state": "not_established",
     "consequence": "Do not rely on an old hearing reference as an invitation to comment today."
    },
    {
     "question": "Documented local positions and delivered benefits",
     "state": "not_researched",
     "consequence": "No view is attributed to a community and no local benefit is assumed."
    },
    {
     "question": "A single site-wide delivery probability",
     "state": "not_applicable",
     "consequence": "This file does not turn scoped permissions or old stages into a probability score."
    }
   ],
   "watchpoints": [
    "A later dated building or commissioning observation with an explicit building scope.",
    "Evidence that either permitted 132 kV line span was constructed and energised.",
    "Current official participation information and evidence of local commitments or outcomes."
   ],
   "next_step": "Inspect the listed line scopes, then seek separately dated evidence for construction and energisation, the relevant building, remaining consents and commissioning.",
   "next_step_url": "https://www.nve.no/konsesjon/konsesjonssaker/konsesjonssak?id=26255&type=A-1"
  },
  {
   "slug": "middenmeer",
   "path": "/projects/middenmeer",
   "title": "Middenmeer: keep the existing record and expansion notice separate",
   "canonical_record_path": "/data-centres/microsoft-middenmeer",
   "country": "NL",
   "locality": "Middenmeer, Hollands Kroon",
   "entity_id": "middenmeer-project-context",
   "catalogue_stage": {
    "value": "operating",
    "as_of": "2022-06-23",
    "source_url": "https://www.tweedekamer.nl/debat_en_vergadering/uitgelicht/datacenters-nederland",
    "checked_on": "2026-10-02",
    "scope": "Retained historical catalogue label, not a fresh whole-project status check or a delivery-confidence score."
   },
   "change_history": {
    "status": "not_established",
    "material_change_detected_at": null,
    "previous_observation_id": null,
    "explanation": "This first connected evidence file assembles existing published observations. It does not establish a newly detected project change or a complete change history. A later source date alone is not evidence that the whole project advanced."
   },
   "summary": "An existing-site reference from 2022 and a 2025 expansion notice concern different evidence scopes. Their physical relationship remains unverified.",
   "scope": "This file concerns Microsoft evidence at Middenmeer, not Google Middenmeer. The older Wieringermeer reference is mapped to Middenmeer in the catalogue. The AMS-E, Deelgebied B1 notice is locality/operator discovery context, not a verified match to that campus or other phases.",
   "supported_position": "The existing record has a historical operating observation dated 23 June 2022. The 30 December 2025 notice records MER preparation for a proposed expansion. Neither establishes the expansion as operating, permitted today or physically identical to the older record.",
   "observation_ids": [
    "middenmeer-historical-site",
    "middenmeer-mer-notice",
    "middenmeer-mer-boundary"
   ],
   "briefing_observation_ids": [
    "middenmeer-mer-notice",
    "middenmeer-mer-boundary"
   ],
   "dependency": "Resolve the project and address association before comparing stages. Inspect later official case materials to establish whether a subsequent permit decision exists; the MER-intent notice is not that decision.",
   "local_implications": "The notice provides a route into the official case evidence. It does not establish a current comment window, local support or opposition, impacts or delivered benefits.",
   "gaps": [
    {
     "question": "Physical association between AMS-E/B1 and the historical record",
     "state": "not_established",
     "consequence": "Do not merge buildings, addresses, capacity or phases on a shared place and company name."
    },
    {
     "question": "Later decisions and current participation status",
     "state": "not_established",
     "consequence": "The historic notice cannot support a present permit or deadline claim."
    },
    {
     "question": "Local effects, public positions and delivery outcomes",
     "state": "not_researched",
     "consequence": "This file cannot balance benefits and burdens or speak for people affected."
    },
    {
     "question": "Whether the two observations contradict each other",
     "state": "not_established",
     "consequence": "Different dates and unresolved identities do not by themselves demonstrate a conflict."
    }
   ],
   "watchpoints": [
    "An official project/address match that resolves the physical association.",
    "Later case documents or decisions with their own publication and event dates.",
    "Current participation information, scoped local-impact evidence and evidence of delivery."
   ],
   "next_step": "Read the official notice and use its document link to inspect the underlying case materials directly, checking for later decisions before relying on current status.",
   "next_step_url": "https://zoek.officielebekendmakingen.nl/prb-2025-21956.html"
  },
  {
   "slug": "hepokorpi",
   "path": "/projects/hepokorpi",
   "title": "Hepokorpi: a phase 3 permit is not evidence of completed delivery",
   "canonical_record_path": "/data-centres/microsoft-hepokorpi-espoo",
   "country": "FI",
   "locality": "Hepokorpi, Espoo",
   "entity_id": "hepokorpi-project-context",
   "catalogue_stage": {
    "value": "under_construction",
    "as_of": "2026-06-11",
    "source_url": "https://www.sttinfo.fi/tiedote/72129950/ymparisto-ja-rakennuslautakunta-hepokorven-datakeskuksen-kolmannelle-vaiheelle-rakennuslupa?lang=fi",
    "checked_on": "2026-10-02",
    "scope": "Retained historical catalogue label, not a fresh whole-project status check or a delivery-confidence score."
   },
   "change_history": {
    "status": "not_established",
    "material_change_detected_at": null,
    "previous_observation_id": null,
    "explanation": "This first connected evidence file assembles existing published observations. It does not establish a newly detected project change or a complete change history. A later source date alone is not evidence that the whole project advanced."
   },
   "summary": "A June 2026 phase 3 permit account sits beside reporting on earlier-phase construction. The permit and programme targets do not establish current operation.",
   "scope": "The phase 3 permit concerns a specific part of the Hepokorpi project. The separate environmental-assessment listing concerns the wider Espoo project area; its conclusions have not been mapped to the phase 3 permit here. Wider Microsoft construction reporting also covers other Finnish locations and cannot be treated as a single-site completion observation.",
   "supported_position": "The existing announcement records a phase 3 building-permit decision on 11 June 2026. The retained catalogue construction label and wider programme account do not establish that phase 3 is built or that the campus is operating now.",
   "observation_ids": [
    "hepokorpi-phase-3-permit",
    "hepokorpi-construction-programme"
   ],
   "briefing_observation_ids": [
    "hepokorpi-phase-3-permit"
   ],
   "dependency": "The Finnish environment administration lists a reasoned conclusion for the Espoo project environmental assessment dated 4 June 2024. Keep this historical listing separate from the June 2026 phase 3 building permit. Inspect the underlying conclusion, compare it with the city decision linked from the catalogue record, and establish which conditions concern the relevant phase before seeking later construction, commissioning and service evidence.",
   "local_implications": "The environmental-assessment page lists a no-build alternative. The underlying assessment, choice of alternative and fulfilment of conditions were not inspected here. The existing record contains planned heat-recovery and cooling context. Plans and expectations do not establish delivered heat, realised local benefits, community consent or current environmental performance.",
   "gaps": [
    {
     "question": "Current phase-specific construction and commissioning",
     "state": "not_established",
     "consequence": "An earlier-phase account cannot establish that phase 3 has reached the same stage."
    },
    {
     "question": "Permit finality and any current participation window",
     "state": "not_established",
     "consequence": "The linked decision is a source to inspect, not current legal advice or an asserted appeal deadline."
    },
    {
     "question": "Delivered heat recovery, local positions and other outcomes",
     "state": "not_researched",
     "consequence": "No benefit is counted as realised and no community position is inferred."
    },
    {
     "question": "Available compute or a site capacity figure",
     "state": "not_established",
     "consequence": "A permit and a multi-location programme account cannot answer an access or available-capacity question."
    }
   ],
   "watchpoints": [
    "The underlying environmental conclusion and any conditions relevant to the specific phase, including how alternatives and local effects were assessed.",
    "Later official decisions and phase-specific construction evidence.",
    "Commissioning and service evidence at Hepokorpi rather than programme-wide targets.",
    "Documented local commitments, heat-recovery delivery and current participation information."
   ],
   "next_step": "Open the official environmental-assessment project page. To compare it with the phase 3 building decision, follow the unchanged planning link in the existing catalogue record above. Confirm the relevant phase, conditions and later evidence directly; historical assessment and permit dates do not establish current legal status, participation or completed delivery.",
   "next_step_url": "https://www.ymparisto.fi/fi/osallistu-ja-vaikuta/ymparistovaikutusten-arviointi/espoon-datakeskusalue-espoo",
   "source_route": {
    "title": "Finnish environment administration: Espoo environmental-assessment project page",
    "url": "https://www.ymparisto.fi/fi/osallistu-ja-vaikuta/ymparistovaikutusten-arviointi/espoon-datakeskusalue-espoo",
    "checked_on": "2026-10-25",
    "independently_reviewed_at": "2026-10-25T15:40:40Z",
    "source_publication_date": "2024-02-04",
    "source_updated_on": "2024-07-09",
    "event_date": "2024-06-04",
    "scope": "Environmental-assessment page listing only: published 4 February 2024, updated 9 July 2024, reasoned conclusion listed 4 June 2024. Two minimal attributed metadata statements and an ordinary source link, with copyright retained and no open content licence asserted. The underlying conclusion, reports, attachments and private submissions were not opened. This is not the phase 3 permit, current participation, fulfilled conditions or completed delivery; older facility observations and their dates remain unchanged."
   }
  }
 ],
 "briefing": {
  "path": "/briefings/progress-towards-usable-compute",
  "title": "What establishes progress towards usable compute?",
  "summary": "Three European evidence files show why construction, electrical permission, environmental assessment and phase-specific permits need to be read separately before drawing conclusions about delivery.",
  "question": "What does the available evidence establish about progress towards delivery, and what does it leave unresolved?",
  "cohort": "Gromstul, Microsoft evidence at Middenmeer and Hepokorpi are an initial selected cohort, not representative global coverage or a ranking.",
  "interpretation": "These files support a narrower conclusion than a single project status suggests: the evidence concerns different steps, dates and physical scopes. A later permission or notice cannot refresh an older construction or operating observation. The next useful research task is the missing link in each case, rather than a larger headline capacity total.",
  "not_established": "These selected observations do not establish current usable capacity, completion probabilities, market-wide delivery pace, net local benefit or which project is furthest ahead.",
  "observation_ids": [
   "gromstul-electrical-licence",
   "gromstul-electrical-line-scope",
   "middenmeer-mer-notice",
   "middenmeer-mer-boundary",
   "hepokorpi-phase-3-permit"
  ]
 }
}