Grid queues and large-load demand evidence

Demand-side statements and generation/storage queues are separate kinds of evidence. The two demand accounts below contain no capacity total; Berkeley Lab's separately dated generation and storage figures follow.

Large-load demand evidence: separate processes and categories

The two accounts below concern demand-side evidence. PJM forecast adjustments are not a load queue. Statnett's reserved and ordinary-queue categories can overlap. Neither account supplies a queue-capacity total, current headroom or a connection guarantee. Do not add these categories to each other or to the generation/storage figures below.

PJM: forecast adjustments, not a load queue

PJM says it has no load-interconnection queue. It uses large-load adjustments submitted by load-serving entities when preparing its long-term load forecast.

Read the official source

Inspect dates, source use and limits
Source publication
29 September 2026
Source update
Not recorded
Event date
Not recorded
Source retrieval
Not recorded
Independent precise-use review
2026-10-31T23:14:15.906Z
Evidence checked
31 October 2026
Source version
Not recorded
Scope
PJM 2027 Long-Term Load Forecast preparation
Quantity / metric
Not recorded; this account is not a queue total

No queue capacity, firm connection commitment, forecast outcome or current commissioning inferred. No consultant findings or utility attachment data imported.

Only minimal independently worded attributed facts and ordinary unframed links are used. No source narrative, table, chart, marks, personal contacts, dataset or full document is copied. No open licence or recurring-monitoring grant is asserted. Reuse terms: No open licence recorded. Source site notice; this link is not a licence grant.

Statnett: queue and reservation category overlap

Statnett distinguishes queued, reserved and connected cases. It says a project with capacity reserved on special conditions can also appear in the queue for ordinary terms.

Read the official source

Inspect dates, source use and limits
Source publication
Not recorded
Source update
Not recorded
Event date
Not recorded
Source retrieval
Not recorded
Independent precise-use review
2026-10-31T23:14:15.906Z
Evidence checked
31 October 2026
Source version
Not recorded
Scope
Statnett connection-case statistics; source data may be incomplete
Quantity / metric
Not recorded; this account is not a queue total

No PowerBI, customer list or download inspected/imported. No numeric total or named project; categories may overlap and must not be summed.

Only minimal independently worded attributed facts and ordinary unframed links are used. No source narrative, table, chart, marks, personal contacts, dataset or full document is copied. No open licence or recurring-monitoring grant is asserted. Reuse terms: No open licence recorded.

Download these same two accounts as JSON or CSV. Their 31 October evidence checks do not renew Berkeley Lab's separate 3 October check.

Generation and storage: what an interconnection queue is

Figures from Berkeley Lab's Queued Up 2026 Edition, covering data to the end of 2025. Each figure is shown with its metric, date and source.

Generation and storage data below: Lawrence Berkeley National Laboratory, in collaboration with GridTracker. Licence: CC BY 4.0. We link to the original and have not changed the figures. We have not added any figures together.

A power plant or battery that wants to plug into the high voltage grid has to ask the grid operator first. The operator studies what the connection would do to the grid and what upgrades it needs. Requests wait in line for those studies, and that line is the interconnection queue. Queued Up counts the projects in these lines.

What it means for data centres

We only state what the source says.

So Queued Up is a record of supply waiting to connect, not of data centre demand. It helps with one question: how much new generation and storage is applying to join each part of the US grid. It does not say how much of that is for data centres.

Headline figures

National figures, 2026 Edition, as read on the Berkeley Lab pages
FigureValueMetricAs ofSource
Active projects seeking interconnectionabout 8,200active requests (count)end of 2025Source
Generation capacity in active queues1,312 GWactive generation capacityend of 2025Source
Storage capacity in active queues749 GWactive storage capacityend of 2025Source
Total capacity in active queues, as stated on the pageover 2,060 GWactive capacity, generation and storage as the source states itend of 2025Source
Change in total active queue volume on the previous yeardown 10%year on year change, total active volumeend of 2025Source
Capacity with a draft or executed interconnection agreement, not yet operating549 GWcapacity with draft or executed agreementend of 2025Source
Median time from interconnection request to commercial operationover 5 yearsmedian duration, request to operationend of 2025Source
Outcome of capacity requested in 2000 to 202013% reached operation, 75% withdrawn, 10% still activeshare of requested capacity by outcome, requests 2000 to 2020end of 2025Source
Coverage of the data fileall 7 ISOs/RTOs and 50 non-ISO utilities, about 98% of installed US generating capacitycoverage of installed US generating capacityend of 2025Source

By region or grid operator

Active queue capacity and number of requests by region, 2026 Edition
RegionCapacity (GW)RequestsAs ofSource
CAISO191.3432end of 2025Source
ERCOT408.01,527end of 2025Source
ISO-NE14.872end of 2025Source
MISO382.21,646end of 2025Source
NYISO29.2190end of 2025Source
PJM144.31,134end of 2025Source
SPP171.2683end of 2025Source
Southeast (non-ISO)152.9957end of 2025Source
West (non-ISO)567.41,603end of 2025Source
All regions, as the source totals them2,0618,244end of 2025Source

Each row counts what is waiting in that region. It is not a measure of how fast or how well an operator connects projects.

By resource type

Active queue capacity by resource type, 2026 Edition
ResourceCapacity (GW)ChangeAs ofSource
Solar773down 19% on the previous yearend of 2025Source
Storage749down 16% on the previous yearend of 2025Source
Wind220down 19% on the previous yearend of 2025Source
Natural gas253up 86% on the previous yearend of 2025Source
Nuclear, geothermal and hydro, combined as the source states it18nuclear up 96%, geothermal up 170%, hydro down 49% on the previous yearend of 2025Source

These rows are the resource types the source reports separately. They do not add up to the national total, and we have not worked out a figure for the rest.

What we do not know

Limits the source states about its own data

Data, licence and credit

The data is compiled by Berkeley Lab in collaboration with GridTracker. The source page states: The Queued Up data file is licensed CC BY 4.0. You may use, share, or adapt the dataset as long as you attribute it to Lawrence Berkeley National Laboratory and GridTracker. Source. Licence text: CC BY 4.0. The wording on the page covers the data file. We copy only short facts and one table of figures, with attribution, and link to the file for anything more.

Checked 3 October 2026. Due for review by 3 January 2027. Spotted a mistake? Tell us. See also sources and licences, grid rules for large loads and news.