ComputeFinder

Power for compute

Grid rules for large loads

11 summaries of what grid operators and regulators say about connecting data centres and other large loads. Each has its operator, region, topic, date and a link to the page it came from.

The summaries are in our own words. We read each source page directly. Where a page shows no date, the date is the day we read it. Figures stay with the entry that states them and are not added together.

What this page is for

A new data centre needs a grid connection, and the rules for getting one differ by operator. This page collects the large load rules, processes and forecasts we have read so far. It is a starting list, not a full register, and it does not cover every operator. A missing operator means we have not read its page yet, not that it has no rules.

Large load rules and statements by operator
OperatorRegionTopicSummaryAs ofSource
ERCOTTexas, United StatesLarge load batch study processERCOT is building a Batch Study process that groups large loads meeting strict requirements into single studies, to give consistent and system-wide results. The working group page lists meetings from December 2025 (workshops from February 2026) and weekly Batch Zero readiness meetings up to July 2026, with nothing scheduled for September.2026-10-03Read the official source
AEMONational Electricity Market, AustraliaData centre connections and demand outlookAEMO calls data centres among the fastest growing sources of demand and says large connections are targeting about two years from application to energisation. Its page counts 11 large transmission pipeline projects above 5MW, and it expects the share of national electricity use to rise by 2030 and 2050. It has also asked the AEMC, through a rule change request, for a clearer and more consistent framework for how large loads connect and perform.2026-06-01Read the official source
AEMONational Electricity Market, AustraliaData centre forecast method and project completion rateAEMO's 2026 forecast overview combines developer project data with economic modelling. It notes that many announced projects have not been built historically, which is why it does not treat the full list of developing sites as expected demand. The overview projects operational consumption from data centres roughly tripling by FY30 under its Step Change scenario.2026-08-25Read the official source
AEMC (for Australian ministers)AustraliaLarge load register and cost recoveryThe energy minister's rule change requests propose a public register of prospective and existing large loads of 5MW or more, prudential arrangements to guard against stranded network assets, and guidance on transmission connection pricing. The AEMC opened consultation on them on 24 September 2026.2026-07-01Read the official source
EirGridIrelandData centre connection offer process (CRU policy implementation)Version 3 of EirGrid's process applies to data centres of 1MVA or more seeking transmission connection. Applicants must show dispatchable on-site or nearby generation matched to import capacity, plus new Irish renewable supply for at least 80% of annual demand over a six-year glide path. Applications in constrained network areas cannot proceed, and EirGrid estimates about 7.5 to 18 months to process complete applications depending on generation status.2026-05-20Read the official source
FERCUnited States (PJM, MISO, SPP, CAISO, ISO-NE, NYISO)Large load show cause ordersOn 18 June 2026 FERC ordered six grid operators to justify or reform their tariffs for large loads, covering transmission service procedures, cost transparency, co-located generation, flexible transmission service and generation serving adjacent loads. Operators had 60 days to respond and 30 days to report on resource adequacy.2026-06-18Read the official source
SPPCentral United StatesHigh Impact Large Load integrationSPP offers a Conditional High Impact Large Load service with expedited access and possible curtailment during system stress, and a generation assessment that studies loads and supporting on-site generation in parallel. It targets interconnection agreements within 90 days and is holding stakeholder question sessions from May to October 2026.2026-10-03Read the official source
PJMMid-Atlantic and Midwest, United StatesLarge load ride-through reliability proposalPJM wants large computational loads to ride through grid disturbances rather than disconnect, after a July 2026 event in northern Virginia when close to 4,000MW of data centre load dropped. It intends to file proposals with FERC in November 2026 and says MISO, ERCOT and NERC are developing similar standards.2026-09-10Read the official source
NESOGreat BritainConnections reform Gate 2 offer timetableNESO's timeline shows Gate 2 offers for transmission and large embedded projects issued in two phases, mid-May to mid-September 2026 and early September 2026 to mid-January 2027, and distribution offers in two phases, early July to mid-November 2026 and mid-October 2026 to mid-March 2027. The page does not break out data centres or other demand, so it is context for queue timing only.2026-10-03Read the official source
Lawrence Berkeley National LaboratoryUnited StatesQueued Up 2026 edition, generation and storage queuesThe 2026 edition reports the active generation and storage queue fell about 10% year on year by end 2025, with gas capacity rising sharply and a median of over five years from request to operation for projects built in 2025. It states that load interconnection requests, including data centres, are not in the dataset, so it should not be read as a measure of data centre queues.2026-05-01Read the official source
TenneT (Netherlands); ACM decisionNetherlandsHistorical TDTR notification timing and release time granularityACM amended the Dutch TDTR code provisions in its decision of 23 April 2026. The amendment changes notification timing and the time granularity used to release capacity.2026-04-23Read the official source

Historical Dutch TDTR amendment

Staatscourant 2026, 17010; ACM/UIT/671095; ACM/25/199016

ACM amended the Dutch TDTR code provisions in its decision of 23 April 2026. The amendment changes notification timing and the time granularity used to release capacity.

This account concerns the historical amendment only. It does not establish current consolidated law, any project's eligibility or available transport capacity. The table's as-of date is the decision event date.

Inspect dates, source use and limits
Source publication
7 May 2026
Source update
Not recorded
Event date
23 April 2026
Source retrieval
Not recorded
Independent precise-use review
2026-10-31T23:14:15.906Z
Evidence checked
31 October 2026
Source version
Not recorded
Instrument
Staatscourant 2026, 17010; ACM/UIT/671095; ACM/25/199016
Recorded version
decision of 23 April 2026
Effective date (calendar inference)
8 May 2026
Inference basis
Calendar consequence of Article II: day after the Gazette issue dated 7 May 2026; separately identified inference, not a retrieval clock.
Applicability
Dutch Systeemcode elektriciteit 2026 TDTR amendment only. Not TenneT Germany, a site-specific offer, or guaranteed unrestricted transport.
Later changes
The amendment supplies its own commencement rule. Consolidated current code and later amendments were not reviewed.

Consolidated TDTR product provisions were not reviewed in this narrow amendment account. No congestion-area headroom or project eligibility is established.

Only minimal independently worded attributed facts and ordinary unframed links are used. No source narrative, table, chart, marks, personal contacts, dataset or full document is copied. No open licence or recurring-monitoring grant is asserted. Reuse terms: No open licence recorded. Source site notice; this link is not a licence grant.

Reading these entries

Related

The ten retained summaries: Checked 3 October 2026. Due for review by 3 January 2027. Spotted a mistake? Tell us. See also sources and licences.