ComputeFinder

Data last collected: 2 October 2026 (Epoch AI data centres only) Data last rechecked: 2 October 2026

Countries / Asia-Pacific and Middle East

Taiwan

Taiwan passed an AI Basic Act in December 2025, and the practical limit on AI data centres is regional grid and substation capacity, not total electricity.

The legislature passed the AI Basic Act on 23 December 2025. It sets principles, names the National Science and Technology Council as competent authority and tasks the Ministry of Digital Affairs with a risk framework; it does not itself impose EU-style obligations on companies. Taipower had received 79 AI data centre power applications totalling about 4,758MW by November 2025, approving 40 (about 3,033MW) and rejecting 39, and over 70 percent of approved capacity then lapsed. For someone seeking compute, northern Taiwan colocation exists but power is the gating item, and the national research supercomputers sit with the NCHC.

AI policy and activity

The Act promises budgets, sandboxes, data opening and infrastructure support. Sector regulators will make detailed rules using the Ministry's risk taxonomy, still to be built.

Power and grid

Reported. The Reporter says data centres use under 1 percent of Taiwan's electricity, so the strain is on regional grids and substations in the north, where projects cluster; approved capacity of about 3,033MW was equal to roughly 1.6 times the installed capacity of the Third Nuclear Power Plant, though most has since lapsed.

Data centres and compute

SiteWhereStatusNotes and source
Vantage Taoyuan data centre (A-TOP Digital and Industrial Park)
Vantage Data Centers
Guishan, TaoyuanOperatingReported. The Reporter says a completed Vantage facility is leased by Taiwan Mobile for NT$8.8 billion. (source)
Westwood data centre
Keppel and DDSP
Guishan, TaoyuanUnder constructionReported. Same article; Taipower is building a 161kV transmission line to serve the area. (source)
Foxconn (Hon Hai) Blackwell supercomputer
Hon Hai Technology Group
Taiwan (site not stated in the article)PlannedReported. The Next Platform (9 October 2024) described Foxconn as an early buyer of Nvidia Blackwell GB200 NVL72 racks; current status was not confirmed. The same article describes NCHC Taiwania 2 (2018) and Taiwania 3, with Taiwania 4 not confirmed as built. (source)

Rules and programmes

InstrumentKindStatusWhat it does
Artificial Intelligence Basic ActLawIn forcePrimary, Ministry of Digital Affairs page (30 April 2026): seven principles, budget and incentive support, sandbox, data openness. Passed 23 December 2025 per Baker McKenzie and TVBS; the promulgation date was not confirmed, so effective_on is null.
Taipower AI data centre power application processGridIn forceReported. The Reporter (20 April 2026): the Ministry of Economic Affairs treats data centres above 5MW as large; approved applications that do not start formal procedures within six months lapse. The underlying Taipower rule was not read.

Checked on 2 October 2026 and due for review by 1 January 2027. Many sources are trade press or law-firm summaries rather than official texts, and statuses such as reported or unconfirmed are shown as the source gives them. This is a summary, not legal advice. If something is wrong or out of date, tell us.

Nearby on this site