OperatingIceland
What we checked
- Verne and Landsnet launched a high-capacity substation at Keflavik on 19 May 2025, rated 240 MW installed with 120 MW operational initially. (source)
- A January 2022 trade report said Verne was adding 20 MW and expected the campus to reach 40 MW of a potential 100 MW. (source)
The 120 MW figure is substation capacity operational at May 2025, not data hall capacity.
Operate this site or have better evidence? .
- Operator
- Verne
- Owner
- Not stated
- Stage
- Operating (source, 19 May 2025)
- Power
- A new Landsnet substation has 240 MW installed, with 120 MW operational at launch and full capacity expected by end of 2026.
Capacity
| Measure | Stage | Basis | MW | As of | Source |
|---|---|---|---|---|---|
| Grid connection | Energised | reported | 120 | 19 May 2025 | source |
These figures measure different things and are not added together.
Printable community case file
Verne Keflavik campus
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Operating, recorded 19 May 2025 | Inspect the stage source and limits |
| Where is the formal decision evidence? | Not recorded here. | First identify whether an application exists and which authority or process applies; then inspect its file, reference, status, consultation window, decision and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 2 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Evidence carried into this printout
- Recorded stage. Operating, dated 19 May 2025: stage source
- Checked statement. Verne and Landsnet launched a high-capacity substation at Keflavik on 19 May 2025, rated 240 MW installed with 120 MW operational initially. source
- Checked statement. A January 2022 trade report said Verne was adding 20 MW and expected the campus to reach 40 MW of a potential 100 MW. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
4 of 13 facility fields recorded
2 separately recorded source statements. These are not included in the facility-field count.
4 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Owner
- Grid connection
- Cooling
- PUE
- Water use
- Chips
- Connectivity
- Certifications
- Planning reference
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Verne Keflavik campus: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/verne-keflavik
BibTeX
@misc{computefinder_data_centres_verne_keflavik,
title = {Verne Keflavik campus: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0051}},
number = {cf-dc-0051},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0051. Permanent link: https://computefinder.net/entity/cf-dc-0051. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/verne-keflavik. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0051"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in Iceland
All detailed records in Iceland / Same recorded stage in Iceland
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact