Data centres / Nordics / Sweden
EcoDataCenter Borlänge campus
Borlänge, former Kvarnsveden mill site, Sweden.
AnnouncedSweden
What we checked
- A 6 September 2024 press release announced a campus of 240 MW or more on a former paper mill site, with first facilities targeted for 2027 once permits are secured. (source)
- A trade report says the site is about 20 hectares and could host up to nine buildings. (source)
The release states 240 MW of power capacity without a metric, and trade press adds up to 360 MW potential. The information is two years old and current status is unknown to us.
Operate this site or have better evidence? .
- Operator
- EcoDataCenter
- Owner
- Not stated
- Stage
- Announced (source, 6 September 2024)
- Power
- The company says the campus will use 100 per cent renewable energy.
Named-campus record context
Named-campus context, with limits
This is ComputeFinder's separate context, outside the Epoch estimate/address datasets; no open operator-source licence is asserted.
EcoDataCenter's own pages name its Borlänge campus EcoDataCenter 2 and list Kvarnsvedsvägen 420. This supplies named-campus context for the retained Epoch name/address, without confirming the same phase or facility boundary.
Inspect the separately retained Epoch record. This is a contextual inference, not a shared building, phase, parcel or physical-facility identity. The records remain separate; no quantities are combined.
Explicit operator site-name, locality, street-address and linked-site context matches the retained publisher name/country/address and the separately retained detailed-campus name/locality. The relationship is a bounded contextual inference, not a physical-facility identity or deduplication decision.
- Equal buildings, phases, site boundary or legal parcel
- Equal owners, users, capacities, metrics, stages, permits or operational status
- Commissioning, available compute, accessible allocation, grid availability or performance
- Verified coordinates, geocoding, centroid or WGS84 point
- A deduplicated global physical-facility count
- Source publication
- Not recorded
- Source update
- Not recorded
- Event date
- Not recorded
- Origin retrieval
- Not recorded
- Source version
- Not recorded
- Context evidence checked
- 1 November 2026
- Independent context review
- 2026-11-01T01:43:25.930Z
EcoDataCenter: operator contact page; operator site page. Minimal independently worded attributed site-name and locality/address facts, plus ordinary unframed links only. No copied source narrative, marketing copy, performance or capacity figure, technical table, database, photograph, logo, map, contact details or form is imported. No open source-content licence, endorsement or recurring-monitoring grant is asserted. The personal-data policy is not a content licence. The original 2 October record and 17 October address checks are unchanged. Epoch's retained credit and source terms remain separate from this operator-source use.
There remain 193 source records; the number of unique physical facilities is not established. Context link JSON and CSV carry this separate account.
Planning
| Decision or document | Status | Date | Review |
|---|---|---|---|
| Municipal council approval of the land agreement (vote scheduled 10 September 2024; outcome not confirmed by us) | Pending | 6 September 2024 |
Printable community case file
EcoDataCenter Borlänge campus
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Announced, recorded 6 September 2024 | Inspect the stage source and limits |
| Where is the formal decision evidence? | 1 planning item recorded | Check the authority's complete file, reference and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 2 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Evidence carried into this printout
- Recorded stage. Announced, dated 6 September 2024: stage source
- Decision evidence. Municipal council approval of the land agreement (vote scheduled 10 September 2024; outcome not confirmed by us): Pending, 6 September 2024.
- Checked statement. A 6 September 2024 press release announced a campus of 240 MW or more on a former paper mill site, with first facilities targeted for 2027 once permits are secured. source
- Checked statement. A trade report says the site is about 20 hectares and could host up to nine buildings. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
4 of 13 facility fields recorded
2 separately recorded source statements. These are not included in the facility-field count.
4 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Owner
- Capacity (MW)
- Grid connection
- Cooling
- PUE
- Water use
- Chips
- Connectivity
- Certifications
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). EcoDataCenter Borlänge campus: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/ecodatacenter-borlange
BibTeX
@misc{computefinder_data_centres_ecodatacenter_borlange,
title = {EcoDataCenter Borlänge campus: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0046}},
number = {cf-dc-0046},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0046. Permanent link: https://computefinder.net/entity/cf-dc-0046. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/ecodatacenter-borlange. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0046"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in Sweden
- EdgeConneX Skellefteå campus
- EcoDataCenter 1, Falun
- Microsoft Sweden Central region (Gävle and Sandviken)
- Microsoft Staffanstorp data centre
- Arrhenius (Linköping University campus)
All detailed records in Sweden / Same recorded stage in Sweden
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact