OperatingSweden
What we checked
- A trade report of 30 August 2022 says Microsoft withdrew a planned 70 MW reserve power expansion at Staffanstorp. (source)
Reported only: in August 2022 Microsoft dropped the expansion and said it would keep operating the existing site with current backup units while seeking a new southern Sweden site.
Operate this site or have better evidence? .
- Operator
- Microsoft
- Owner
- Microsoft
- Stage
- Operating (source, 30 August 2022)
- Power
- The withdrawn permit application was for 70 MW of reserve (backup) power, which is not IT or grid capacity.
Planning
| Decision or document | Status | Date | Review |
|---|---|---|---|
| Permit application for reserve power expansion (70 MW of backup power) dropped | Withdrawn | 30 August 2022 |
Printable community case file
Microsoft Staffanstorp data centre
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Operating, recorded 30 August 2022 | Inspect the stage source and limits |
| Where is the formal decision evidence? | 1 planning item recorded | Check the authority's complete file, reference and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 1 checked statement and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Evidence carried into this printout
- Recorded stage. Operating, dated 30 August 2022: stage source
- Decision evidence. Permit application for reserve power expansion (70 MW of backup power) dropped: Withdrawn, 30 August 2022.
- Checked statement. A trade report of 30 August 2022 says Microsoft withdrew a planned 70 MW reserve power expansion at Staffanstorp. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
5 of 13 facility fields recorded
1 separately recorded source statement. These are not included in the facility-field count.
5 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Capacity (MW)
- Grid connection
- Cooling
- PUE
- Water use
- Chips
- Connectivity
- Certifications
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Microsoft Staffanstorp data centre: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/microsoft-staffanstorp
BibTeX
@misc{computefinder_data_centres_microsoft_staffanstorp,
title = {Microsoft Staffanstorp data centre: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0048}},
number = {cf-dc-0048},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0048. Permanent link: https://computefinder.net/entity/cf-dc-0048. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/microsoft-staffanstorp. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0048"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in Sweden
- EdgeConneX Skellefteå campus
- EcoDataCenter 1, Falun
- EcoDataCenter Borlänge campus
- Microsoft Sweden Central region (Gävle and Sandviken)
- Arrhenius (Linköping University campus)
All detailed records in Sweden / Same recorded stage in Sweden
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact