Sweden is reworking how large electricity users queue for and gain grid connection.

The government told the transmission operator in September 2025 to review its connection process to shorten lead times. Its April 2026 report proposes a readiness-based element alongside first-come, first-served, capacity zones for chosen customer types, and an investigation of fossil-free supply requirements for large new users. These are proposals, and neither text names data centres specifically.

Power and grid

The operator's report says first-come, first-served can tie up capacity with projects that are not ready, which is why it proposes a readiness test.

The rules and programmes

InstrumentKindStatusWhat it does
Government assignment to review the connection processGridended
from 9 September 2025
Assignment published 9 September 2025 with a reporting deadline of 30 April 2026; the press release does not mention data centres.
Svenska kraftnat report on connection and market accessGridproposedDated 29 April 2026; proposes a first-ready mechanism, capacity zones and further study of supply agreements for large consumers.

Checked against the primary sources linked above on 2 October 2026. Due for review by 1 January 2027. This is a summary, not legal advice. If something is out of date, tell us.