- The IEA notes data centres cluster in specific locations, which can make grid integration harder, and that energy infrastructure takes longer to build than data centres (IEA).
What we checked
- The IEA estimates data centres used around 415 TWh in 2024, about 1.5 percent of global electricity. (source)
- Its base case reaches around 945 TWh by 2030, just under 3 percent of global electricity. (source)