Supply chain / Electrical

US transformer supply and lead times

A 2023 US Government Accountability Office report documented longer delivery times for large power and distribution transformers and heavy reliance on imports.

Type
Reported constraint
Where it sits
Long transformer waits can delay grid connection for new data centres, so they affect when announced capacity can actually come online.
Constraint
The GAO reported lead times lengthening to years for some utilities, and said over 80 percent of large power transformers used in the US in 2019 were imported (GAO-23-106180, August 2023).

What we checked

Visit the source

Written by ComputeFinder from public pages on 2 October 2026. Company statements are the company's own, not independently checked, and reported items are marked as such. Not yet reviewed line by line by a second person. If something is wrong, tell us.