Ireland CRU data centre connection policy

Ireland's energy regulator decided in December 2025 on conditions for new large data centre grid connections.

Type
Programme
Where it sits
It shows how a regulator can tie grid access to on-site or local generation and storage, which shapes where capacity can be built in Ireland.
Constraint
Grid access depends on meeting the CRU's requirements, including generation or storage matching maximum import demand (CRU decision).