Ireland's energy regulator decided in December 2025 on conditions for new large data centre grid connections.
- Type
- Programme
- Where it sits
- It shows how a regulator can tie grid access to on-site or local generation and storage, which shapes where capacity can be built in Ireland.
- Constraint
- Grid access depends on meeting the CRU's requirements, including generation or storage matching maximum import demand (CRU decision).
What we checked
- The CRU decision of 12 December 2025 requires data centres to provide generation and/or storage, onsite or local, to match maximum import demand. (source)
- It requires at least 80 percent of annual electricity from new Irish renewable projects, with a six-year development timeline allowed. (source)
Written by ComputeFinder from public pages on 2 October 2026. Company statements are the company's own, not independently checked, and reported items are marked as such. Not yet reviewed line by line by a second person. If something is wrong, tell us.