Data centres / Nordics / Norway
Gromstul data centre (Project Telemark), Skien
Gromstul, Skien, Telemark, Norway.
Stage not knownNorway
What we checked
- The municipal zoning plan was proposed by Skien municipality to enable power- and space-intensive uses, primarily data centres, with a cap of 500 parking spaces. (source)
- A Skanska-related report puts the 2024 groundworks contract for WS Computing at the Gromstul site at about NOK 1.1 billion. (source)
- Trade press said the mayor played down a widely quoted 860 MW figure as a long-range estimate for the whole industrial area, not one tenant's request. (source)
Permit documents name WS Computing AS as applicant and do not name the end user. Trade press has linked the Gromstul campus to Google, which we treat as reported only. The 100 MW figure is from 2023 and may be out of date.
What the evidence establishes
A historical construction account and a later electrical-installation licence establish different parts of the evidence picture. Neither establishes usable compute today.
The existing record retains a Building 1 construction observation from December 2025. The separately reviewed NVE case lists electrical-installation permission dated 28 August 2026; another page for that case names two permitted 132 kV line spans. These listings do not update the old building-stage observation or establish completed electrical work.
Scope: The Gromstul project context includes historical Building 1 and proposed Building 2 reporting, beside a separately scoped NVE electrical case. These are not interchangeable campus-wide stages.
What to check next
The NVE listing identifies two permitted 132 kV line scopes. Seek separately dated evidence for their construction and energisation, the relevant building, remaining consents and commissioning.
Inspect the listed line scopes, then seek separately dated evidence for construction and energisation, the relevant building, remaining consents and commissioning. Open the official source.
Read the connected evidence
Gromstul: construction and electrical permission have different scopes
What establishes progress towards usable compute?
These related reading routes explain dated evidence, unresolved dependencies and next questions. They do not update this record's facts, stage or checked date.
Operate this site or have better evidence? .
- Operator
- WS Computing AS
- Owner
- Not stated
- Stage
- Stage not known
- Power
- A trade report quoting the mayor in November 2023 said 100 MW of grid power was then granted, with 20 MW awaiting approval and 120 MW more hoped for a second stage towards 2030.
- Cooling
- The noise assessment for Building 2 lists 70 outdoor cooling units; the zoning plan allows heat recovery installations.
- Grid connection
- NVE lists case 202607246 as licence granted, dated 28 August 2026. A separate page for the same case identifies two 132 kV line scopes in its title: Building 1 to Building 2, and Gromstul switch station to the data-centre transformer station. (132 kV)
Scope: The two line spans identified in NVE case 202607246 at case-HTML/title grain only: Building 1 to Building 2, and Gromstul switch station to the data-centre transformer station. The permitted stage applies only to these listed line scopes. Construction, energisation, commissioning, all campus consents, current operation, capacity and available compute are not established.. Stage: Permitted. Basis: permitted. Evidence: official source. Evidence date: 28 August 2026. source. Source version: not established. Source published: not stated; source updated: not stated; retrieved: not recorded; reviewed: 2026-10-25T16:32:51.701Z; evidence checked: 25 October 2026.
NVE and relevant underlying rightsholders: Source copyright retained; exact basic-fact use assessed only. One minimal attributed case/title fact and ordinary unframed case link only. No source narrative, quotations, attachments, maps, drawings, images, contacts, tables or datasets reproduced or adapted. No open licence, public-domain status, endorsement, blanket domain clearance or recurring-monitoring grant. The earlier inspected NVE open-data notice applies NLOD to api.nve.no data, not automatically this case HTML or attachments. Existing source-use review was read but is not treated as blanket permission; the exact candidate was independently reviewed.
Separate scoped statements, not a whole-site operating or availability claim. Values are not combined across scopes, stages, metrics or sites.
- NVE lists case 202607246 as licence granted, dated 28 August 2026. A separate page for the same case identifies two 132 kV line scopes in its title: Building 1 to Building 2, and Gromstul switch station to the data-centre transformer station. (132 kV)
Capacity
| Measure | Stage | Basis | MW | As of | Source |
|---|---|---|---|---|---|
| Grid connection | Permitted | reported | 100 | 22 November 2023 | source |
These figures measure different things and are not added together.
Planning
| Decision or document | Status | Date | Review |
|---|---|---|---|
| Detailed zoning plan for Gromstul data centre (plan ID 2017004), Skien municipality | Approved | Not stated |
Gromstul electrical-installation evidence
- NVE lists the Gromstul electrical-installation case as licence granted, dated 28 August 2026, and says permission was given to WS Computing AS for electrical installations linked to the data centre in Skien.
- NVE case 202607246 lists the electrical-installation licence and related documents.
NVE: Gromstul electrical-installation case. Open the NVE case page to inspect its listed electrical-installation decision and related documents directly.
Scoped decision evidence checked 17 October 2026; next review by 23 October 2026. Source publication and update dates are not stated. The inspected evidence is the case HTML, not the underlying decision PDF or attachments. Electrical-installation permission does not establish all campus consents, legal finality, a current comment or appeal window, completion, commissioning, current operation, capacity or available compute. WS Computing AS is the named permission recipient, not newly verified campus owner, operator or end user. Earlier campus facts, stage, capacity and source dates are unchanged; no building or phase is split or merged.
NVE and relevant underlying rightsholders: Source copyright retained; exact basic-fact use assessed only. Two minimal attributed basic case facts and ordinary unframed case link only. No source narrative, quotations, attachments, maps, drawings, images, contacts, tables or datasets reproduced or adapted. No open licence, public-domain status, endorsement, blanket domain clearance or recurring-monitoring grant. The inspected NVE open-data notice applies NLOD to api.nve.no data, not automatically this case HTML or attachments; no API data was acquired. No applicable express restriction was visible in the complete case and inspected notices; this is not proof that no broader terms exist. Reassess newly evidenced applicable conditions without a paraphrase workaround.
Printable community case file
Gromstul data centre (Project Telemark), Skien
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Stage not known, recorded 12 December 2025 | Inspect the stage source and limits |
| Where is the formal decision evidence? | 1 planning item recorded | Check the authority's complete file, reference and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 3 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Gromstul electrical-installation evidence
- NVE lists the Gromstul electrical-installation case as licence granted, dated 28 August 2026, and says permission was given to WS Computing AS for electrical installations linked to the data centre in Skien.
- NVE case 202607246 lists the electrical-installation licence and related documents.
NVE: Gromstul electrical-installation case. Open the NVE case page to inspect its listed electrical-installation decision and related documents directly.
Scoped decision evidence checked 17 October 2026; next review by 23 October 2026. Source publication and update dates are not stated. The inspected evidence is the case HTML, not the underlying decision PDF or attachments. Electrical-installation permission does not establish all campus consents, legal finality, a current comment or appeal window, completion, commissioning, current operation, capacity or available compute. WS Computing AS is the named permission recipient, not newly verified campus owner, operator or end user. Earlier campus facts, stage, capacity and source dates are unchanged; no building or phase is split or merged.
NVE and relevant underlying rightsholders: Source copyright retained; exact basic-fact use assessed only. Two minimal attributed basic case facts and ordinary unframed case link only. No source narrative, quotations, attachments, maps, drawings, images, contacts, tables or datasets reproduced or adapted. No open licence, public-domain status, endorsement, blanket domain clearance or recurring-monitoring grant. The inspected NVE open-data notice applies NLOD to api.nve.no data, not automatically this case HTML or attachments; no API data was acquired. No applicable express restriction was visible in the complete case and inspected notices; this is not proof that no broader terms exist. Reassess newly evidenced applicable conditions without a paraphrase workaround.
Connected evidence to revisit
- Gromstul: construction and electrical permission have different scopes
https://computefinder.net/projects/gromstul - What establishes progress towards usable compute?
https://computefinder.net/briefings/progress-towards-usable-compute
These related reading routes explain dated evidence, unresolved dependencies and next questions. They do not update this record's facts, stage or checked date.
Evidence carried into this printout
- Recorded stage. Stage not known, with no stage source recorded.
- Decision evidence. Detailed zoning plan for Gromstul data centre (plan ID 2017004), Skien municipality: Approved, date not stated.
- Checked statement. The municipal zoning plan was proposed by Skien municipality to enable power- and space-intensive uses, primarily data centres, with a cap of 500 parking spaces. source
- Checked statement. A Skanska-related report puts the 2024 groundworks contract for WS Computing at the Gromstul site at about NOK 1.1 billion. source
- Checked statement. Trade press said the mayor played down a widely quoted 860 MW figure as a long-range estimate for the whole industrial area, not one tenant's request. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
6 of 13 facility fields recorded
3 separately recorded source statements. These are not included in the facility-field count.
6 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Owner
- Stage
- PUE
- Water use
- Chips
- Connectivity
- Certifications
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Gromstul data centre (Project Telemark), Skien: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/skien-gromstul-telemark
BibTeX
@misc{computefinder_data_centres_skien_gromstul_telemark,
title = {Gromstul data centre (Project Telemark), Skien: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0032}},
number = {cf-dc-0032},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0032. Permanent link: https://computefinder.net/entity/cf-dc-0032. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/skien-gromstul-telemark. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0032"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in Norway
All detailed records in Norway / Same recorded stage in Norway
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact