Vantage Cardiff campus (CWL1, Newport)

OperatingUnited Kingdom6 of 13 fields known

Newport, South Wales (Vantage calls it Cardiff), United Kingdom.

Operator
Vantage Data Centers
Owner
Not stated
Stage
Operating (source, 2 October 2026)
Power
Vantage says a dedicated 400kV substation on campus connects privately to the national grid and that all power into the campus is renewable.
Cooling
Vantage says the climate supports free air cooling for much of the year and cites air-to-air plate heat exchange.
Certifications
ISO 9001, ISO 14001, ISO/IEC 27001, ISO 45001, ISAE 3402, SOC 2

Vantage gives 72MW existing and 148MW of critical IT load once fully developed; both are operator statements on an undated page. Certifications are Vantage corporate listings, not site audits. The Bridgend planning report refers to this as the existing Newport campus.

Capacity

MeasureStageBasisMWAs ofSource
IT loadOperatingreported722 October 2026source
IT loadAnnouncedreported1482 October 2026source

These figures measure different things and are not added together.

What we checked

What we do not know yet

6 of 13 fields in a complete record are filled. Still missing:

Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.

Other sites in United Kingdom