SDC M40 Campus, Wapseys Wood

AnnouncedUnited Kingdom5 of 13 fields known

Wapseys Wood landfill site, Buckinghamshire, United Kingdom.

Operator
Not stated
Owner
Not stated
Stage
Announced (source, 16 March 2026)
Power
The scheme includes an on-site gas energy centre with maximum generating capacity of roughly 250 to 350MW, per the Planning Inspectorate project page.
Cooling
Air cooling is proposed.

Proposal stage. The 300MW is the applicant's proposed IT load across three buildings of about 100MW each, as recorded in the Secretary of State's direction. The applicant named in the direction is Slough Holdings UK Limited; the end operator is not stated.

Capacity

MeasureStageBasisMWAs ofSource
IT loadAnnouncedreported30016 March 2026source

These figures measure different things and are not added together.

Planning

What we checked

What we do not know yet

5 of 13 fields in a complete record are filled. Still missing:

Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.