Trinidad and Tobago signed preliminary agreements in July 2026 for up to 800 MW of data centres, with water and power still to be solved.

On 11 July 2026 the prime minister signed memorandums of understanding with Hummingbird AI and EY for data centres at Debe, a designated special economic zone. They are reported as up to 800 MW in total, with Hummingbird targeting first commercial operation in Q1 2028. The government projects US$5 billion of investment. These are preliminary and no facility exists. For someone seeking compute, treat this as a pipeline, not capacity.

Power and grid

The report says solar is planned to grow, citing 8.37 MW of solar in 2024 and a projection of 336.24 MW by 2029. That is small next to the proposed load, and we did not read how gas-fired supply would be handled.

Data centres and compute

Data centres and compute
SiteWhereStatusNotes and source
Debe data centre zone
Hummingbird AI and EY with developers
DebePlannedUp to 800 MW across both MoUs. The public utilities minister said projects would need hybrid water solutions including man-made ponds and eventually desalination. (source)

Rules and programmes

Rules and programmes
InstrumentKindStatusWhat it does
Data centre MoUs with Hummingbird AI and EY
Read the cited source
ProgrammeProposed
from 11 July 2026
Trade report: EY 300 MW with third-party developers; Hummingbird 150 MW initially, expandable to 500 MW. Described as the first such agreements with a Caribbean country.

Checked on 2 October 2026 and due for review by 1 January 2027. Many sources are trade press or law-firm summaries rather than official texts, and statuses such as reported or unconfirmed are shown as the source gives them. This is a summary, not legal advice. If something is wrong or out of date, tell us.

Cite this page

ComputeFinder. (2026, October 2). Trinidad and Tobago: AI and compute. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/countries/trinidad-and-tobago

BibTeX
@misc{computefinder_countries_trinidad_and_tobago,
  title        = {Trinidad and Tobago: AI and compute},
  author       = {{ComputeFinder}},
  year         = {2026},
  howpublished = {\url{https://computefinder.net/entity/cf-ctry-0038}},
  number       = {cf-ctry-0038},
  note         = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}

Stable ID: cf-ctry-0038. Permanent link: https://computefinder.net/entity/cf-ctry-0038. It keeps working if this page moves.

Page link: https://computefinder.net/countries/trinidad-and-tobago. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.

Share this record

Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.

Listed on ComputeFinder

Embed code
<a href="https://computefinder.net/entity/cf-ctry-0038"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>

More in Americas

How we label evidence
  • Official source the body that made the rule or the data says so
  • Two sources agree independent sources match
  • One source, not confirmed a single report or claim
  • Watching a signal, not shown as a fact