QTS Cambois Data Centre Campus

Cambois, Blyth, Northumberland, United Kingdom.

PermittedUnited Kingdom

What we checked

Council news item dated 2 December 2025 reports approval of phase one; the date shown is the news date, not necessarily the committee date. No MW figure was found in a fetched primary source, so capacity is left empty.

Operate this site or have better evidence? .

Operator
QTS
Owner
Blackstone
Stage
Permitted (source, 2 December 2025)
Power
The government press release for the North East AI Growth Zone says the zone as a whole will reach 1.1GW of energy capacity within six years, but it does not say which metric that is or how much belongs to Cambois.
Cooling
The council says the scheme will use a closed loop water system.

Planning

Planning
Decision or documentStatusDateReview
First phase approved by Northumberland Strategic Planning Committee: first two of up to ten data centre buildingsApproved2 December 2025

Printable community case file

QTS Cambois Data Centre Campus

Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.

Use this record as a shared case file

This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.

Use this record as a shared case file
QuestionWhat this record currently showsUseful next step
What stage is evidenced?Permitted, recorded 2 December 2025Inspect the stage source and limits
Where is the formal decision evidence?1 planning item recordedCheck the authority's complete file, reference and conditions
How can the public participate?Northumberland planning application search and comment route
Checked 5 October 2026. This is the council's general planning participation route. ComputeFinder has not recorded a current Cambois comment deadline.
Use the recorded route for its stated purpose and verify its current status; identify the responsible authority or process separately and do not infer a live window from this record
Which promises became outcomes?Review 3 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome.Keep proposed, committed and delivered states separate, with dates and responsible parties

Evidence carried into this printout

  • Recorded stage. Permitted, dated 2 December 2025: stage source
  • Decision evidence. First phase approved by Northumberland Strategic Planning Committee: first two of up to ten data centre buildings: Approved, 2 December 2025.
  • Checked statement. Councillors approved the first phase, which covers the first two of up to ten data centre buildings planned for the Cambois campus. source
  • Checked statement. The full campus is described as up to 540,000 square metres of floorspace, with about 400 staff forecast once fully operational. source
  • Checked statement. A government release of 16 September 2025 quotes a regional leader saying the QTS Cambois campus is due to open in 2028, and states that Blackstone has committed 10 billion pounds to the Blyth site. source

Named next steps

Next decision and owner:

Participation route and deadline:

Evidence still required:

Review date:

Open the community questions guide

Permanent case-file link

This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.

What we do not know yet

These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.

6 of 13 facility fields recorded

3 separately recorded source statements. These are not included in the facility-field count.

6 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:

Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.

Cite this page

ComputeFinder. (2026, October 2). QTS Cambois Data Centre Campus: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/qts-cambois-blyth

BibTeX
@misc{computefinder_data_centres_qts_cambois_blyth,
  title        = {QTS Cambois Data Centre Campus: capacity, planning and power},
  author       = {{ComputeFinder}},
  year         = {2026},
  howpublished = {\url{https://computefinder.net/entity/cf-dc-0001}},
  number       = {cf-dc-0001},
  note         = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}

Stable ID: cf-dc-0001. Permanent link: https://computefinder.net/entity/cf-dc-0001. It keeps working if this page moves.

Page link: https://computefinder.net/data-centres/qts-cambois-blyth. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.

Share this record

Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.

Listed on ComputeFinder

Embed code
<a href="https://computefinder.net/entity/cf-dc-0001"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>

Other sites in United Kingdom

All detailed records in United Kingdom / Same recorded stage in United Kingdom

How we label evidence
  • Official source the body that made the rule or the data says so
  • Two sources agree independent sources match
  • One source, not confirmed a single report or claim
  • Watching a signal, not shown as a fact