Data centres / UK and Ireland / United Kingdom
Dartford AI data centre campus, New Barn Road
Dartford, Kent, United Kingdom.
AnnouncedUnited Kingdom
What we checked
- The Secretary of State directed on 1 July 2026 that an AI data centre campus of up to four buildings on land adjacent to New Barn Road, Dartford, be treated as needing a development consent order. (source)
- The direction states a proposed total power load of up to 300MW and IT load of up to 240MW. (source)
Proposal stage. The figures are the applicant's proposed totals for up to four buildings, recorded in the direction dated 1 July 2026: 240MW IT load and 300MW total power load. The applicant is named as CSE52 Limited; the end operator is not stated.
Operate this site or have better evidence? .
- Operator
- Not stated
- Owner
- Not stated
- Stage
- Announced (source, 1 July 2026)
- Power
- The direction records a total power load of up to 300MW alongside associated energy and utility works.
Inspect the limits of this source check
These notes describe a bounded inspection, not a whole planning-application audit. They do not count as recorded facility fields, prove that information does not exist elsewhere or refresh this record's check date.
- Grid connection, PUE, Water use, Chips, Coordinates: Not stated in the inspected source. The selected short official Section35 direction/decision identifies the named proposal and procedure, not a voltage/substation connection, explicit design/target/measured PUE, scoped water measurement/period, chips or official point/CRS. No IT/total-power ratio is converted to PUE; air cooling or a proposed energy centre is not zero-water or a delivered grid connection. No broader planning/EIA/utility audit or whole-application omission is claimed. Scope recorded 1 November 2026; inspected source context. MHCLG / GOV.UK: Crown/source rights retained; no new document-component OGL grant asserted. Only an original selected-official-filing inspection-limit account and ordinary link. No directive/report text, developer evidence, map, contact, capacity figure, narrative adaptation or underlying dataset is imported. A different independent review completed at 2026-11-01T03:10:26.335Z accepts only this original account of the selected two-page official direction and an ordinary link. GOV.UK terms were directly read: ordinary links are encouraged subject to the stated charged-click-through and endorsement limits. General Crown/OGL language is conditional; no new document-component open-licence grant is asserted. No source text, developer evidence, map, contact, technical capacity figure or underlying dataset is imported. The retained National Archives route was not requested.
Capacity
| Measure | Stage | Basis | MW | As of | Source |
|---|---|---|---|---|---|
| IT load | Announced | reported | 240 | 1 July 2026 | source |
| Facility load | Announced | reported | 300 | 1 July 2026 | source |
These figures measure different things and are not added together.
Planning
| Decision or document | Status | Date | Review |
|---|---|---|---|
| Section 35 direction treating the campus as development needing a development consent order (a procedural direction, not a consent) | Status not known | 1 July 2026 |
Printable community case file
Dartford AI data centre campus, New Barn Road
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Announced, recorded 1 July 2026 | Inspect the stage source and limits |
| Where is the formal decision evidence? | 1 planning item recorded | Check the authority's complete file, reference and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 2 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Evidence carried into this printout
- Recorded stage. Announced, dated 1 July 2026: stage source
- Decision evidence. Section 35 direction treating the campus as development needing a development consent order (a procedural direction, not a consent): Status not known, 1 July 2026.
- Checked statement. The Secretary of State directed on 1 July 2026 that an AI data centre campus of up to four buildings on land adjacent to New Barn Road, Dartford, be treated as needing a development consent order. source
- Checked statement. The direction states a proposed total power load of up to 300MW and IT load of up to 240MW. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
4 of 13 facility fields recorded
2 separately recorded source statements. These are not included in the facility-field count.
4 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Owner
- Operator
- Grid connection
- Cooling
- PUE
- Water use
- Chips
- Connectivity
- Certifications
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Dartford AI data centre campus, New Barn Road: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/dartford-new-barn-road-ai-campus
BibTeX
@misc{computefinder_data_centres_dartford_new_barn_road_ai_campus,
title = {Dartford AI data centre campus, New Barn Road: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0014}},
number = {cf-dc-0014},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0014. Permanent link: https://computefinder.net/entity/cf-dc-0014. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/dartford-new-barn-road-ai-campus. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0014"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in United Kingdom
- QTS Cambois Data Centre Campus
- Cobalt Park, Wallsend (Stargate UK, North East AI Growth Zone)
- Culham AI Growth Zone (UKAEA Culham Campus)
- Nscale Loughton AI Campus
- Google Waltham Cross data centre
All detailed records in United Kingdom / Same recorded stage in United Kingdom
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact