Microsoft Hepokorpi data centre, Espoo

Hepokorpi, Espoo, Finland.

Under constructionFinland

What we checked

Permits for the first two phases on the northern plot were already granted and construction is under way. No site MW figure was found.

What the evidence establishes

A June 2026 phase 3 permit account sits beside reporting on earlier-phase construction. The permit and programme targets do not establish current operation.

The existing announcement records a phase 3 building-permit decision on 11 June 2026. The retained catalogue construction label and wider programme account do not establish that phase 3 is built or that the campus is operating now.

Scope: The phase 3 permit concerns a specific part of the Hepokorpi project. The separate environmental-assessment listing concerns the wider Espoo project area; its conclusions have not been mapped to the phase 3 permit here. Wider Microsoft construction reporting also covers other Finnish locations and cannot be treated as a single-site completion observation.

What to check next

The Finnish environment administration lists a reasoned conclusion for the Espoo project environmental assessment dated 4 June 2024. Keep this historical listing separate from the June 2026 phase 3 building permit. Inspect the underlying conclusion, compare it with the city decision linked from the catalogue record, and establish which conditions concern the relevant phase before seeking later construction, commissioning and service evidence.

Open the official environmental-assessment project page. To compare it with the phase 3 building decision, follow the unchanged planning link in the existing catalogue record above. Confirm the relevant phase, conditions and later evidence directly; historical assessment and permit dates do not establish current legal status, participation or completed delivery. Open the official source.

Read the connected evidence

Hepokorpi: a phase 3 permit is not evidence of completed delivery

What establishes progress towards usable compute?

These related reading routes explain dated evidence, unresolved dependencies and next questions. They do not update this record's facts, stage or checked date.

Operate this site or have better evidence? .

Operator
Microsoft
Owner
Microsoft 3465 Finland Oy
Stage
Under construction (source, 11 June 2026)
Power
Microsoft says its Finnish programme is backed by renewable energy agreements totalling over 200 MW.
Cooling
Waste heat is to be recovered with Fortum for district heating; the 2022 town hall material expected mainly air cooling with rainwater supplement in hot weather.
Grid connection
  • Fingrid's 2022 plan described a 400/110 kV Hepokorpi substation and a planned Microsoft data-centre connection.
    Scope: Historical shared-substation plan published 16 May 2022 only. The two voltage levels stay textual. No Microsoft supply voltage, completed connection, energisation, phase-three mapping or present operation is established.. Stage: Announced. Basis: reported. Evidence: official source. Evidence date: not stated. source. Source version: not established. Source published: 16 May 2022; source updated: not stated; retrieved: not recorded; reviewed: 2026-10-31T22:55:44.727Z; evidence checked: 31 October 2026.
    Fingrid Oyj: Copyright retained; no open licence verified. The inspected notice conditions other-material use on unchanged material and attribution.. A minimal independently worded identification of a historical project plan with an ordinary source link. No source prose, quotations, technical table, market dataset, photograph, trademark asset or contact details are copied. Prior YLE2021 ordinary-link clearance does not cover this separately reviewed named-project technical statement. Source: Fingrid Oyj, 16 May 2022 project announcement; original linked in source_url. No endorsement is implied. This exact minimal factual use was independently assessed against the unchanged-material condition, separately from copied or modified source material and the notice's commercial market-information restriction. No new right or blanket commercial reuse permission is declared.

Separate scoped statements, not a whole-site operating or availability claim. Values are not combined across scopes, stages, metrics or sites.

Inspect the limits of this source check

These notes describe a bounded inspection, not a whole planning-application audit. They do not count as recorded facility fields, prove that information does not exist elsewhere or refresh this record's check date.

  • PUE, Water use, Chips, Coordinates: Not inspected in this scope. This admission checks a historical shared-substation plan in one Fingrid announcement. It does not audit the underlying EIA, later building or phase records, equipment schedules or numeric parcel coordinates for these unfilled fields. Scope recorded 31 October 2026; inspected source context. Fingrid Oyj: Copyright retained; no open licence verified. The inspected notice conditions other-material use on unchanged material and attribution.. A minimal independently worded identification of a historical project plan with an ordinary source link. No source prose, quotations, technical table, market dataset, photograph, trademark asset or contact details are copied. Prior YLE2021 ordinary-link clearance does not cover this separately reviewed named-project technical statement. Source: Fingrid Oyj, 16 May 2022 project announcement; original linked in source_url. No endorsement is implied. This exact minimal factual use was independently assessed against the unchanged-material condition, separately from copied or modified source material and the notice's commercial market-information restriction. No new right or blanket commercial reuse permission is declared.

Planning

Planning
Decision or documentStatusDateReview
Phase 3 building permit for the data centre, Espoo environment and building boardApproved11 June 2026

Printable community case file

Microsoft Hepokorpi data centre, Espoo

Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.

Use this record as a shared case file

This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.

Use this record as a shared case file
QuestionWhat this record currently showsUseful next step
What stage is evidenced?Under construction, recorded 11 June 2026Inspect the stage source and limits
Where is the formal decision evidence?1 planning item recordedCheck the authority's complete file, reference and conditions
How can the public participate?Not recorded here. Record the official route, deadline, decision-maker and how responses are considered
Which promises became outcomes?Review 3 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome.Keep proposed, committed and delivered states separate, with dates and responsible parties

Connected evidence to revisit

These related reading routes explain dated evidence, unresolved dependencies and next questions. They do not update this record's facts, stage or checked date.

Evidence carried into this printout

  • Recorded stage. Under construction, dated 11 June 2026: stage source
  • Decision evidence. Phase 3 building permit for the data centre, Espoo environment and building board: Approved, 11 June 2026.
  • Checked statement. On 11 June 2026 the Espoo environment and building board approved a phase 3 building permit for Microsoft 3465 Finland Oy and allowed work to begin before the permit is final. source
  • Checked statement. The 2022 town hall summary expected air cooling as the main method and recovery of 70 to 85 per cent of heat for district heating. source
  • Checked statement. Microsoft said in April 2026 that first-phase construction began in late 2024 and should finish around the turn of 2026 to 2027, with second-phase work starting in 2026 at Espoo, Kirkkonummi and Vihti. source

Named next steps

Next decision and owner:

Participation route and deadline:

Evidence still required:

Review date:

Open the community questions guide

Permanent case-file link

This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.

What we do not know yet

These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.

7 of 13 facility fields recorded

3 separately recorded source statements. These are not included in the facility-field count.

7 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:

Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.

Cite this page

ComputeFinder. (2026, October 2). Microsoft Hepokorpi data centre, Espoo: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/microsoft-hepokorpi-espoo

BibTeX
@misc{computefinder_data_centres_microsoft_hepokorpi_espoo,
  title        = {Microsoft Hepokorpi data centre, Espoo: capacity, planning and power},
  author       = {{ComputeFinder}},
  year         = {2026},
  howpublished = {\url{https://computefinder.net/entity/cf-dc-0039}},
  number       = {cf-dc-0039},
  note         = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}

Stable ID: cf-dc-0039. Permanent link: https://computefinder.net/entity/cf-dc-0039. It keeps working if this page moves.

Page link: https://computefinder.net/data-centres/microsoft-hepokorpi-espoo. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.

Share this record

Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.

Listed on ComputeFinder

Embed code
<a href="https://computefinder.net/entity/cf-dc-0039"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>

Other sites in Finland

All detailed records in Finland / Same recorded stage in Finland

How we label evidence
  • Official source the body that made the rule or the data says so
  • Two sources agree independent sources match
  • One source, not confirmed a single report or claim
  • Watching a signal, not shown as a fact