Microsoft Kirkkonummi data centre campus

Kirkkonummi, Finland.

Under constructionFinland

What we checked

Microsoft says building permits are in hand for all three Helsinki-region campuses for phase 2. The revoked crushing permit concerns site works only, and we do not know whether it was reissued.

Operate this site or have better evidence? .

Operator
Microsoft
Owner
Microsoft 3465 Finland Oy
Stage
Under construction (source, 28 April 2026)
Cooling
Waste heat recovery with Fortum is central to the plan, with the company projecting it could cover about 40 per cent of heating for the district heating network when fully operating.
Grid connection
  • The authority’s Kirkkonummi account records two planned 400 kV underground circuits from Fingrid’s Mankki substation to Kolabacken. (400 kV)
    Scope: Only the proposed Kirkkonummi project described in authority case UUDELY/8117/2023. This is the authority’s account of the applicant’s plan, not a grid approval, connection right, constructed/energised link, current facility operation or available compute. Voltage class is separate from circuit count and MW/MVA capacity; no conversion or total is derived. Permanent planned Kolabacken supply route only. 400 kV is the class of each named circuit. No commissioning/connection event date is established.. Stage: Announced. Basis: reported. Evidence: official source. Evidence date: not stated. source. Source version: not established. Source published: not stated; source updated: not stated; retrieved: not recorded; reviewed: 2026-11-01T02:53:38.785Z; evidence checked: 1 November 2026.
    Uudenmaan ELY-keskus, Finland: No open source-content licence or public-domain determination made for this component. Three minimal independently worded attributed voltage/substation-route facts from the public authority reasoned-conclusion project-description section, with an ordinary unframed link. No source report passage/translation, diagram, map, figure, table, performance/capacity total, developer EIAR, personal contact or underlying dataset is imported. Uudenmaan ELY-keskus, reasoned conclusion UUDELY/8117/2023, dated 9 July 2024; selected project-description paragraph, printed pp2-3. Original authority PDF linked in source_url. No endorsement. Selected planned voltage classes and named endpoints reduced to original short English factual accounts. Not an official translation. The authority is summarising the applicant’s project description, not independently certifying constructed links. Only the exact minimal basic-fact/link proposal is prepared under the user-authorised audit. No express use restriction for that precise proposal was visible in the selected public authority document sections or the inspected portal About/responsibility page. This is not permission inferred from an absent notice, a blanket government/public-domain/OGL grant or a clearance of developer/consultant materials. Source rights and third-party expression remain excluded; A separate independent factual and exact-use assessment completed at 2026-11-01T02:53:38.785Z accepts only these minimal basic facts and ordinary links. No source-content licence, ownership ruling or recurring acquisition permission follows.
  • The same project account records a separate planned 110 kV backup link from Fingrid’s Framnäs substation to Hammars. (110 kV)
    Scope: Only the proposed Kirkkonummi project described in authority case UUDELY/8117/2023. This is the authority’s account of the applicant’s plan, not a grid approval, connection right, constructed/energised link, current facility operation or available compute. Voltage class is separate from circuit count and MW/MVA capacity; no conversion or total is derived. Backup Hammars route only, kept separate from the Kolabacken supply and temporary construction connections. No energisation or construction completion is established.. Stage: Announced. Basis: reported. Evidence: official source. Evidence date: not stated. source. Source version: not established. Source published: not stated; source updated: not stated; retrieved: not recorded; reviewed: 2026-11-01T02:53:38.785Z; evidence checked: 1 November 2026.
    Uudenmaan ELY-keskus, Finland: No open source-content licence or public-domain determination made for this component. Three minimal independently worded attributed voltage/substation-route facts from the public authority reasoned-conclusion project-description section, with an ordinary unframed link. No source report passage/translation, diagram, map, figure, table, performance/capacity total, developer EIAR, personal contact or underlying dataset is imported. Uudenmaan ELY-keskus, reasoned conclusion UUDELY/8117/2023, dated 9 July 2024; selected project-description paragraph, printed pp2-3. Original authority PDF linked in source_url. No endorsement. Selected planned voltage classes and named endpoints reduced to original short English factual accounts. Not an official translation. The authority is summarising the applicant’s project description, not independently certifying constructed links. Only the exact minimal basic-fact/link proposal is prepared under the user-authorised audit. No express use restriction for that precise proposal was visible in the selected public authority document sections or the inspected portal About/responsibility page. This is not permission inferred from an absent notice, a blanket government/public-domain/OGL grant or a clearance of developer/consultant materials. Source rights and third-party expression remain excluded; A separate independent factual and exact-use assessment completed at 2026-11-01T02:53:38.785Z accepts only these minimal basic facts and ordinary links. No source-content licence, ownership ruling or recurring acquisition permission follows.
  • Before those substations, the project account proposes two 20 kV underground construction-supply connections from Caruna’s Masala substation. (20 kV)
    Scope: Only the proposed Kirkkonummi project described in authority case UUDELY/8117/2023. This is the authority’s account of the applicant’s plan, not a grid approval, connection right, constructed/energised link, current facility operation or available compute. Voltage class is separate from circuit count and MW/MVA capacity; no conversion or total is derived. Temporary construction supply only. It is not the planned permanent grid supply or proof that works had begun. No actual connection date or capacity is established.. Stage: Announced. Basis: reported. Evidence: official source. Evidence date: not stated. source. Source version: not established. Source published: not stated; source updated: not stated; retrieved: not recorded; reviewed: 2026-11-01T02:53:38.785Z; evidence checked: 1 November 2026.
    Uudenmaan ELY-keskus, Finland: No open source-content licence or public-domain determination made for this component. Three minimal independently worded attributed voltage/substation-route facts from the public authority reasoned-conclusion project-description section, with an ordinary unframed link. No source report passage/translation, diagram, map, figure, table, performance/capacity total, developer EIAR, personal contact or underlying dataset is imported. Uudenmaan ELY-keskus, reasoned conclusion UUDELY/8117/2023, dated 9 July 2024; selected project-description paragraph, printed pp2-3. Original authority PDF linked in source_url. No endorsement. Selected planned voltage classes and named endpoints reduced to original short English factual accounts. Not an official translation. The authority is summarising the applicant’s project description, not independently certifying constructed links. Only the exact minimal basic-fact/link proposal is prepared under the user-authorised audit. No express use restriction for that precise proposal was visible in the selected public authority document sections or the inspected portal About/responsibility page. This is not permission inferred from an absent notice, a blanket government/public-domain/OGL grant or a clearance of developer/consultant materials. Source rights and third-party expression remain excluded; A separate independent factual and exact-use assessment completed at 2026-11-01T02:53:38.785Z accepts only these minimal basic facts and ordinary links. No source-content licence, ownership ruling or recurring acquisition permission follows.

Separate scoped statements, not a whole-site operating or availability claim. Values are not combined across scopes, stages, metrics or sites.

Inspect the limits of this source check

These notes describe a bounded inspection, not a whole planning-application audit. They do not count as recorded facility fields, prove that information does not exist elsewhere or refresh this record's check date.

  • PUE, Water use, Chips, Coordinates: Not stated in the inspected source. Only the reasoned conclusion’s project identity and grid project-description paragraphs on printed pages 1 to 3 were freshly inspected for this proposal, with two selected PUE/water keyword lookups whose nonmatches do not establish absence. Those paragraphs did not establish an explicitly scoped PUE, water withdrawal/consumption/WUE measurement and period, chip identifier or verified point/CRS. The rest of the report, developer assessment and utility/parcel files were not audited; no document-wide or planning-application omission, physical absence or zero is claimed. Scope recorded 1 November 2026; inspected source context. Uudenmaan ELY-keskus, Finland: No open source-content licence or public-domain determination made for this component. Three minimal independently worded attributed voltage/substation-route facts from the public authority reasoned-conclusion project-description section, with an ordinary unframed link. No source report passage/translation, diagram, map, figure, table, performance/capacity total, developer EIAR, personal contact or underlying dataset is imported. Uudenmaan ELY-keskus, reasoned conclusion UUDELY/8117/2023, dated 9 July 2024; selected project-description paragraph, printed pp2-3. Original authority PDF linked in source_url. No endorsement. Selected planned voltage classes and named endpoints reduced to original short English factual accounts. Not an official translation. The authority is summarising the applicant’s project description, not independently certifying constructed links. Only the exact minimal basic-fact/link proposal is prepared under the user-authorised audit. No express use restriction for that precise proposal was visible in the selected public authority document sections or the inspected portal About/responsibility page. This is not permission inferred from an absent notice, a blanket government/public-domain/OGL grant or a clearance of developer/consultant materials. Source rights and third-party expression remain excluded; A separate independent factual and exact-use assessment completed at 2026-11-01T02:53:38.785Z accepts only these minimal basic facts and ordinary links. No source-content licence, ownership ruling or recurring acquisition permission follows.

Printable community case file

Microsoft Kirkkonummi data centre campus

Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.

Use this record as a shared case file

This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.

Use this record as a shared case file
QuestionWhat this record currently showsUseful next step
What stage is evidenced?Under construction, recorded 28 April 2026Inspect the stage source and limits
Where is the formal decision evidence?Not recorded here. First identify whether an application exists and which authority or process applies; then inspect its file, reference, status, consultation window, decision and conditions
How can the public participate?Not recorded here. Record the official route, deadline, decision-maker and how responses are considered
Which promises became outcomes?Review 2 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome.Keep proposed, committed and delivered states separate, with dates and responsible parties

Evidence carried into this printout

  • Recorded stage. Under construction, dated 28 April 2026: stage source
  • Checked statement. Microsoft's April 2026 statement says it holds building permits for the second phase at Espoo, Kirkkonummi and Vihti. source
  • Checked statement. The original March 2022 announcement named Espoo, Kauniainen and Kirkkonummi and a district heating scheme using recycled data centre heat. source

Named next steps

Next decision and owner:

Participation route and deadline:

Evidence still required:

Review date:

Open the community questions guide

Permanent case-file link

This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.

What we do not know yet

These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.

5 of 13 facility fields recorded

2 separately recorded source statements. These are not included in the facility-field count.

5 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:

Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.

Cite this page

ComputeFinder. (2026, October 2). Microsoft Kirkkonummi data centre campus: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/microsoft-kirkkonummi

BibTeX
@misc{computefinder_data_centres_microsoft_kirkkonummi,
  title        = {Microsoft Kirkkonummi data centre campus: capacity, planning and power},
  author       = {{ComputeFinder}},
  year         = {2026},
  howpublished = {\url{https://computefinder.net/entity/cf-dc-0040}},
  number       = {cf-dc-0040},
  note         = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}

Stable ID: cf-dc-0040. Permanent link: https://computefinder.net/entity/cf-dc-0040. It keeps working if this page moves.

Page link: https://computefinder.net/data-centres/microsoft-kirkkonummi. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.

Share this record

Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.

Listed on ComputeFinder

Embed code
<a href="https://computefinder.net/entity/cf-dc-0040"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>

Other sites in Finland

All detailed records in Finland / Same recorded stage in Finland

How we label evidence
  • Official source the body that made the rule or the data says so
  • Two sources agree independent sources match
  • One source, not confirmed a single report or claim
  • Watching a signal, not shown as a fact