Data centres / Western Europe / Netherlands
Microsoft Middenmeer data centre
Middenmeer, Hollands Kroon, Netherlands.
OperatingNetherlands
What we checked
- The Dutch parliament's 23 June 2022 page lists an existing Microsoft hyperscale data centre in Wieringermeer; this record maps it to Middenmeer. (source)
- Regional news on 9 September 2025 said Microsoft bought land for a second Middenmeer data centre and expected about a year to obtain permits. (source)
The Dutch parliament page dated 23 June 2022 lists an existing Microsoft hyperscale data centre in Wieringermeer. This record maps it to Middenmeer. The stage date is a historical operating observation, not an exact opening day or a current status check. The separately reported expansion remains pending; no MW or hectares were stated.
What the evidence establishes
An existing-site reference from 2022 and a 2025 expansion notice concern different evidence scopes. Their physical relationship remains unverified.
The existing record has a historical operating observation dated 23 June 2022. The 30 December 2025 notice records MER preparation for a proposed expansion. Neither establishes the expansion as operating, permitted today or physically identical to the older record.
Scope: This file concerns Microsoft evidence at Middenmeer, not Google Middenmeer. The older Wieringermeer reference is mapped to Middenmeer in the catalogue. The AMS-E, Deelgebied B1 notice is locality/operator discovery context, not a verified match to that campus or other phases.
What to check next
Resolve the project and address association before comparing stages. Inspect later official case materials to establish whether a subsequent permit decision exists; the MER-intent notice is not that decision.
Read the official notice and use its document link to inspect the underlying case materials directly, checking for later decisions before relying on current status. Open the official source.
Read the connected evidence
Middenmeer: keep the existing record and expansion notice separate
What establishes progress towards usable compute?
These related reading routes explain dated evidence, unresolved dependencies and next questions. They do not update this record's facts, stage or checked date.
Operate this site or have better evidence? .
- Operator
- Microsoft
- Owner
- Microsoft
- Stage
- Operating (source, 23 June 2022)
- Cooling
- A report says the planned expansion would include rainwater harvesting and water features.
Planning
| Decision or document | Status | Date | Review |
|---|---|---|---|
| Planned second data centre at Middenmeer: land bought and plans shown to Hollands Kroon council; permits expected to take about a year | Pending | 9 September 2025 |
Middenmeer MER-intent notice context
- A Noord-Holland notice published on 30 December 2025 records a MER preparation notification for Microsoft Datacenters Netherlands B.V.'s proposed AMS-E, Deelgebied B1 expansion at Westlanderweg 50, Middenmeer, case OD2025-0043382.
- The notice states that the MER procedure does not itself decide the environmental permit; that decision follows completion of the MER and submission of a permit application.
Noord-Holland: AMS-E, Deelgebied B1 MER-intent notice. Read the official notice and use its document link to inspect the underlying case materials directly, checking for later decisions before relying on current status.
Scoped decision evidence checked 17 October 2026; next review by 23 October 2026. Source publication: 30 December 2025. Source update date is not stated. This supplement is locality/operator discovery context beside the older Microsoft Middenmeer record, not a verified physical-campus or phase association. AMS-E, Deelgebied B1 and Westlanderweg 50 are not matched to Westlanderweg 150, AMS13/14, AMS15/40 or Campus West in the separate coordination decision. The underlying case documents, NRD, PDFs, applications and later decisions were not inspected. This historic notice does not establish current permitting, legal finality, a current comment or appeal window, construction, operation, capacity or available compute. Earlier facility facts, stages, planning and source dates remain unchanged; no building or phase is split or merged.
Province of Noord-Holland and relevant underlying rightsholders: Source copyright retained; exact basic-fact use assessed only. Two minimal attributed basic notice facts and ordinary unframed original link only, not source narrative translation, adaptation or legal advice. No quotations, applicant documents, attachments, maps, drawings, images, contacts, tables or datasets reproduced or adapted. No open licence, public-domain status, endorsement, blanket domain clearance or recurring-monitoring grant. The inspected KOOP CC0 notice is limited to its own website, not this provincial notice or third-party attachments. No express restriction on the bounded basic-fact/link use was visible in the inspected notice HTML; inaccessible Overheid help/reuse conditions remain uninspected, not permission inferred from absence. Reassess newly evidenced applicable conditions without a paraphrase workaround.
Printable community case file
Microsoft Middenmeer data centre
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Operating, recorded 23 June 2022 | Inspect the stage source and limits |
| Where is the formal decision evidence? | 1 planning item recorded | Check the authority's complete file, reference and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 2 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Middenmeer MER-intent notice context
- A Noord-Holland notice published on 30 December 2025 records a MER preparation notification for Microsoft Datacenters Netherlands B.V.'s proposed AMS-E, Deelgebied B1 expansion at Westlanderweg 50, Middenmeer, case OD2025-0043382.
- The notice states that the MER procedure does not itself decide the environmental permit; that decision follows completion of the MER and submission of a permit application.
Noord-Holland: AMS-E, Deelgebied B1 MER-intent notice. Read the official notice and use its document link to inspect the underlying case materials directly, checking for later decisions before relying on current status.
Scoped decision evidence checked 17 October 2026; next review by 23 October 2026. Source publication: 30 December 2025. Source update date is not stated. This supplement is locality/operator discovery context beside the older Microsoft Middenmeer record, not a verified physical-campus or phase association. AMS-E, Deelgebied B1 and Westlanderweg 50 are not matched to Westlanderweg 150, AMS13/14, AMS15/40 or Campus West in the separate coordination decision. The underlying case documents, NRD, PDFs, applications and later decisions were not inspected. This historic notice does not establish current permitting, legal finality, a current comment or appeal window, construction, operation, capacity or available compute. Earlier facility facts, stages, planning and source dates remain unchanged; no building or phase is split or merged.
Province of Noord-Holland and relevant underlying rightsholders: Source copyright retained; exact basic-fact use assessed only. Two minimal attributed basic notice facts and ordinary unframed original link only, not source narrative translation, adaptation or legal advice. No quotations, applicant documents, attachments, maps, drawings, images, contacts, tables or datasets reproduced or adapted. No open licence, public-domain status, endorsement, blanket domain clearance or recurring-monitoring grant. The inspected KOOP CC0 notice is limited to its own website, not this provincial notice or third-party attachments. No express restriction on the bounded basic-fact/link use was visible in the inspected notice HTML; inaccessible Overheid help/reuse conditions remain uninspected, not permission inferred from absence. Reassess newly evidenced applicable conditions without a paraphrase workaround.
Connected evidence to revisit
- Middenmeer: keep the existing record and expansion notice separate
https://computefinder.net/projects/middenmeer - What establishes progress towards usable compute?
https://computefinder.net/briefings/progress-towards-usable-compute
These related reading routes explain dated evidence, unresolved dependencies and next questions. They do not update this record's facts, stage or checked date.
Evidence carried into this printout
- Recorded stage. Operating, dated 23 June 2022: stage source
- Decision evidence. Planned second data centre at Middenmeer: land bought and plans shown to Hollands Kroon council; permits expected to take about a year: Pending, 9 September 2025.
- Checked statement. The Dutch parliament's 23 June 2022 page lists an existing Microsoft hyperscale data centre in Wieringermeer; this record maps it to Middenmeer. source
- Checked statement. Regional news on 9 September 2025 said Microsoft bought land for a second Middenmeer data centre and expected about a year to obtain permits. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
5 of 13 facility fields recorded
2 separately recorded source statements. These are not included in the facility-field count.
5 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Capacity (MW)
- Power source
- Grid connection
- PUE
- Water use
- Chips
- Connectivity
- Certifications
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Microsoft Middenmeer data centre: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/microsoft-middenmeer
BibTeX
@misc{computefinder_data_centres_microsoft_middenmeer,
title = {Microsoft Middenmeer data centre: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0054}},
number = {cf-dc-0054},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0054. Permanent link: https://computefinder.net/entity/cf-dc-0054. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/microsoft-middenmeer. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0054"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in Netherlands
- Google Eemshaven data centre
- Google Middenmeer data centre
- Groningen AI Factory (Zernike, Eurofiber data centre)
- Meta Zeewolde data centre (cancelled)
- Equinix Amsterdam IBX sites (metro cluster)
All detailed records in Netherlands / Same recorded stage in Netherlands
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact