Schwarz Digits Lübbenau data centre

Lübbenau, Spreewald, Brandenburg, Germany.

Under constructionGermany

What we checked

Groundbreaking was 17 November 2025 on a 13-hectare former power plant site, with two phases and completion targeted for end of 2027. Capacity comes from the general contractor, not the owner.

Operate this site or have better evidence? .

Operator
Schwarz Digits (STACKIT)
Owner
Schwarz Group
Stage
Under construction (source, 17 November 2025)
Power
The contractor describes about 200 MW of connection capacity.
Cooling
A trade report says the site will be liquid cooled with waste heat for local district heating; the contractor release does not mention cooling.

Capacity

Capacity
MeasureStageBasisMWAs ofSource
Grid connectionUnder constructionreported20017 November 2025source

These figures measure different things and are not added together.

Printable community case file

Schwarz Digits Lübbenau data centre

Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.

Use this record as a shared case file

This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.

Use this record as a shared case file
QuestionWhat this record currently showsUseful next step
What stage is evidenced?Under construction, recorded 17 November 2025Inspect the stage source and limits
Where is the formal decision evidence?Not recorded here. First identify whether an application exists and which authority or process applies; then inspect its file, reference, status, consultation window, decision and conditions
How can the public participate?Not recorded here. Record the official route, deadline, decision-maker and how responses are considered
Which promises became outcomes?Review 2 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome.Keep proposed, committed and delivered states separate, with dates and responsible parties

Evidence carried into this printout

  • Recorded stage. Under construction, dated 17 November 2025: stage source
  • Checked statement. The general contractor says groundbreaking was 17 November 2025 for a campus with about 200 MW of connection capacity and up to 100,000 processors, finishing by end of 2027. source
  • Checked statement. A trade report says the investment is EUR 11 billion and the site reuses a former power station area. source

Named next steps

Next decision and owner:

Participation route and deadline:

Evidence still required:

Review date:

Open the community questions guide

Permanent case-file link

This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.

What we do not know yet

These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.

6 of 13 facility fields recorded

2 separately recorded source statements. These are not included in the facility-field count.

6 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:

Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.

Cite this page

ComputeFinder. (2026, October 2). Schwarz Digits Lübbenau data centre: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/schwarz-luebbenau

BibTeX
@misc{computefinder_data_centres_schwarz_luebbenau,
  title        = {Schwarz Digits Lübbenau data centre: capacity, planning and power},
  author       = {{ComputeFinder}},
  year         = {2026},
  howpublished = {\url{https://computefinder.net/entity/cf-dc-0059}},
  number       = {cf-dc-0059},
  note         = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}

Stable ID: cf-dc-0059. Permanent link: https://computefinder.net/entity/cf-dc-0059. It keeps working if this page moves.

Page link: https://computefinder.net/data-centres/schwarz-luebbenau. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.

Share this record

Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.

Listed on ComputeFinder

Embed code
<a href="https://computefinder.net/entity/cf-dc-0059"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>

Other sites in Germany

All detailed records in Germany / Same recorded stage in Germany

How we label evidence
  • Official source the body that made the rule or the data says so
  • Two sources agree independent sources match
  • One source, not confirmed a single report or claim
  • Watching a signal, not shown as a fact