Data centres / Western Europe / Germany
Schwarz Digits Lübbenau data centre
Lübbenau, Spreewald, Brandenburg, Germany.
Under constructionGermany
What we checked
- The general contractor says groundbreaking was 17 November 2025 for a campus with about 200 MW of connection capacity and up to 100,000 processors, finishing by end of 2027. (source)
- A trade report says the investment is EUR 11 billion and the site reuses a former power station area. (source)
Groundbreaking was 17 November 2025 on a 13-hectare former power plant site, with two phases and completion targeted for end of 2027. Capacity comes from the general contractor, not the owner.
Operate this site or have better evidence? .
- Operator
- Schwarz Digits (STACKIT)
- Owner
- Schwarz Group
- Stage
- Under construction (source, 17 November 2025)
- Power
- The contractor describes about 200 MW of connection capacity.
- Cooling
- A trade report says the site will be liquid cooled with waste heat for local district heating; the contractor release does not mention cooling.
Capacity
| Measure | Stage | Basis | MW | As of | Source |
|---|---|---|---|---|---|
| Grid connection | Under construction | reported | 200 | 17 November 2025 | source |
These figures measure different things and are not added together.
Printable community case file
Schwarz Digits Lübbenau data centre
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Under construction, recorded 17 November 2025 | Inspect the stage source and limits |
| Where is the formal decision evidence? | Not recorded here. | First identify whether an application exists and which authority or process applies; then inspect its file, reference, status, consultation window, decision and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 2 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Evidence carried into this printout
- Recorded stage. Under construction, dated 17 November 2025: stage source
- Checked statement. The general contractor says groundbreaking was 17 November 2025 for a campus with about 200 MW of connection capacity and up to 100,000 processors, finishing by end of 2027. source
- Checked statement. A trade report says the investment is EUR 11 billion and the site reuses a former power station area. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
6 of 13 facility fields recorded
2 separately recorded source statements. These are not included in the facility-field count.
6 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Grid connection
- PUE
- Water use
- Chips
- Connectivity
- Certifications
- Planning reference
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Schwarz Digits Lübbenau data centre: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/schwarz-luebbenau
BibTeX
@misc{computefinder_data_centres_schwarz_luebbenau,
title = {Schwarz Digits Lübbenau data centre: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0059}},
number = {cf-dc-0059},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0059. Permanent link: https://computefinder.net/entity/cf-dc-0059. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/schwarz-luebbenau. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0059"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in Germany
- KDO data centre, Oldenburg
- German Climate Computing Centre (DKRZ), Hamburg
- Telekom Industrial AI Cloud, Munich (Tucherpark)
- JUPITER exascale system, Forschungszentrum Jülich
- HLRS Stuttgart (Hunter and HammerHAI)
All detailed records in Germany / Same recorded stage in Germany
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact