OperatingFinland
What we checked
- In October 2024 Nebius announced tripling the Finnish site to 75 MW capacity (metric not defined) and up to 60,000 GPUs at full expansion. (source)
- Nebius says heat recovery at the site yields about 20,000 MWh a year. (source)
Nebius states 75 MW of capacity after expansion but does not define the metric, so it is not in the structured field. Later Nebius material says the site hosts GB300 NVL72 systems.
Operate this site or have better evidence? .
- Operator
- Nebius
- Owner
- Nebius
- Stage
- Operating (source, 8 October 2024)
- Cooling
- The company cites free cooling, a heat recovery system warming about 2,500 Finnish homes and a PUE of 1.1 at high IT loads.
Inspect the limits of this source check
These notes describe a bounded inspection, not a whole planning-application audit. They do not count as recorded facility fields, prove that information does not exist elsewhere or refresh this record's check date.
- PUE: No field value admitted. A conditional operator PUE assertion was actually read, but the source does not give the explicit design/target/measured kind or measurement period needed for the present canonical typed field. The separate source-only unknown-kind proposal is not a schema-valid/admitted field and keeps its numeric value null. Scope recorded 1 November 2026; inspected source context. Nebius: Copyright retained; no open-content licence verified for these newsroom releases.. Minimal independently worded attributed basic technical facts and ordinary unframed exact source links only. No copied source expression, specification table, marketing narrative, marks, assets, personal contact, source body or dataset import. Nebius; exact original linked in source_url. No endorsement. Minimal independently worded attributed source account and ordinary link only; no source narrative, quotation, table, graphic, contact or dataset imported. A different independent factual and exact-use review completed at 2026-11-01T03:23:36.511Z. KEEP only the exact minimal independently worded attributed newsroom fact account and ordinary unframed link. The actual newsroom footer and linked Terms of Use of the Nebius Platform were inspected, including Platform/service copying/distribution restrictions. No express condition on this narrow original basic-fact/link account was identified; this does not declare the newsroom outside all terms, imply an open licence, blanket permission, historical-purpose exception or recurring-use grant. Source copyright is retained; no release prose, quotation, table, asset, contact or dataset is imported. Announced/conditional statements retain their original dated scope.
- Grid connection, Water use, Chips, Coordinates: Not inspected in this scope. The selected issuer release is not a grid-filing, water-accounting or coordinate/CRS audit. Historical H100/H200 deployment statements and forward-looking other-platform statements are not imported into a site-current chip inventory. No voltage/substation, bounded water quantity or verified point is admitted. Old parent checks remain unchanged. Scope recorded 1 November 2026; inspected source context. Nebius: Copyright retained; no open-content licence verified for these newsroom releases.. Minimal independently worded attributed basic technical facts and ordinary unframed exact source links only. No copied source expression, specification table, marketing narrative, marks, assets, personal contact, source body or dataset import. Nebius; exact original linked in source_url. No endorsement. Minimal independently worded attributed source account and ordinary link only; no source narrative, quotation, table, graphic, contact or dataset imported. A different independent factual and exact-use review completed at 2026-11-01T03:23:36.511Z. KEEP only the exact minimal independently worded attributed newsroom fact account and ordinary unframed link. The actual newsroom footer and linked Terms of Use of the Nebius Platform were inspected, including Platform/service copying/distribution restrictions. No express condition on this narrow original basic-fact/link account was identified; this does not declare the newsroom outside all terms, imply an open licence, blanket permission, historical-purpose exception or recurring-use grant. Source copyright is retained; no release prose, quotation, table, asset, contact or dataset is imported. Announced/conditional statements retain their original dated scope.
Printable community case file
Nebius Mäntsälä data centre
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Operating, recorded 8 October 2024 | Inspect the stage source and limits |
| Where is the formal decision evidence? | Not recorded here. | First identify whether an application exists and which authority or process applies; then inspect its file, reference, status, consultation window, decision and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 2 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Evidence carried into this printout
- Recorded stage. Operating, dated 8 October 2024: stage source
- Checked statement. In October 2024 Nebius announced tripling the Finnish site to 75 MW capacity (metric not defined) and up to 60,000 GPUs at full expansion. source
- Checked statement. Nebius says heat recovery at the site yields about 20,000 MWh a year. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
4 of 13 facility fields recorded
2 separately recorded source statements. These are not included in the facility-field count.
4 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Capacity (MW)
- Power source
- Grid connection
- PUE
- Water use
- Chips
- Connectivity
- Certifications
- Planning reference
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Nebius Mäntsälä data centre: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/nebius-mantsala
BibTeX
@misc{computefinder_data_centres_nebius_mantsala,
title = {Nebius Mäntsälä data centre: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0041}},
number = {cf-dc-0041},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0041. Permanent link: https://computefinder.net/entity/cf-dc-0041. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/nebius-mantsala. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0041"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in Finland
- Google Hamina data centre
- Microsoft Hepokorpi data centre, Espoo
- Microsoft Kirkkonummi data centre campus
- Nebius Lappeenranta AI factory
- LUMI-AI AI Factory system, CSC Kajaani
All detailed records in Finland / Same recorded stage in Finland
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact