PermittedFrance
What we checked
- The Seine-et-Marne prefecture authorised the project on 29 July 2026 for about 89 hectares, eleven data centre buildings and one training building. (source)
- The local authority calendar says phase 1 construction begins in September 2026 with first delivery of three data centres and the substation estimated in early 2028. (source)
- The same calendar says Mistral AI secured up to 200 MW of computing capacity as founding client, a figure whose metric is not defined. (source)
- The public debate commission's summary gives phase 1 as three data centres plus a training facility and phase 2 as nine more, on about 70 hectares. (source)
The 1.4 GW figure is a power need described by press and the national public debate summary, not a stated IT capacity. Opponents have announced a legal challenge; we did not confirm one has been filed. The project owner or operator is not named in the primary documents we read.
Operate this site or have better evidence? .
- Operator
- Not stated
- Owner
- Not stated
- Stage
- Permitted (source, 29 July 2026)
- Power
- The public debate summary describes 1,400 MW total power need, with a 700 MW provisional connection for phase 1 by 2028, via two 400 kV RTE lines.
- Cooling
- Rooftop refrigeration units are planned instead of groundwater use, with waste heat for a training centre, greenhouses and a nearby prison.
Capacity
| Measure | Stage | Basis | MW | As of | Source |
|---|---|---|---|---|---|
| Grid connection | Permitted | reported | 1400 | 29 July 2026 | source |
These figures measure different things and are not added together.
Planning
| Decision or document | Status | Date | Review |
|---|---|---|---|
| Prefectoral authorisation for the Campus IA installation, Seine-et-Marne | Approved | 29 July 2026 | |
| Local authority project calendar: environmental decree July 2026, phase 1 construction permit August 2026 | Approved | Not stated |
Printable community case file
Campus IA, Fouju
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Permitted, recorded 29 July 2026 | Inspect the stage source and limits |
| Where is the formal decision evidence? | 2 planning items recorded | Check the authority's complete file, reference and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 4 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Evidence carried into this printout
- Recorded stage. Permitted, dated 29 July 2026: stage source
- Decision evidence. Prefectoral authorisation for the Campus IA installation, Seine-et-Marne: Approved, 29 July 2026.
- Decision evidence. Local authority project calendar: environmental decree July 2026, phase 1 construction permit August 2026: Approved, date not stated.
- Checked statement. The Seine-et-Marne prefecture authorised the project on 29 July 2026 for about 89 hectares, eleven data centre buildings and one training building. source
- Checked statement. The local authority calendar says phase 1 construction begins in September 2026 with first delivery of three data centres and the substation estimated in early 2028. source
- Checked statement. The same calendar says Mistral AI secured up to 200 MW of computing capacity as founding client, a figure whose metric is not defined. source
- Checked statement. The public debate commission's summary gives phase 1 as three data centres plus a training facility and phase 2 as nine more, on about 70 hectares. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
5 of 13 facility fields recorded
4 separately recorded source statements. These are not included in the facility-field count.
5 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Owner
- Operator
- Grid connection
- PUE
- Water use
- Chips
- Connectivity
- Certifications
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Campus IA, Fouju: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/campus-ia-fouju
BibTeX
@misc{computefinder_data_centres_campus_ia_fouju,
title = {Campus IA, Fouju: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0066}},
number = {cf-dc-0066},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0066. Permanent link: https://computefinder.net/entity/cf-dc-0066. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/campus-ia-fouju. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0066"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in France
- Phoenix Group Lyon AI data-centre project
- Eclairion Bruyères-le-Châtel
- Digital Realty Paris South (Mistral AI cluster)
- Data4 Paris-Saclay campus (PAR01, PAR02, PAR03)
- Fluidstack France 1 GW AI supercomputer
All detailed records in France / Same recorded stage in France
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact