- An Coimisiun Pleanala refused the appeal for modifications to the permitted Plot 100 data centre on 19 February 2025. (source)
- The application was accompanied by a Natura Impact Statement and an environmental impact assessment report. (source)
The modifications were refused on 19 February 2025, but the case description refers to an earlier permitted data centre on the plot (SD21A/0186), so the underlying permission is treated as standing. This was not independently confirmed. The 45MW and 125MW figures are gas connection and generation, not data hall capacity.
Operate this site or have better evidence? .
- Operator
- Equinix
- Owner
- Not stated
- Stage
- Permitted (source, 19 February 2025)
- Power
- The inspector's report records a Gas Networks Ireland confirmation of a 45MW gas connection for the permitted development, and a separately permitted gas-fired plant with an electrical output of up to 125MW.
Planning
| Decision or document | Status | Date | Review |
|---|---|---|---|
| PL06S.317936 (SD22A/0156): ten-year permission for modifications to the permitted data centre SD21A/0186, refused on appeal | Refused | 19 February 2025 |
Printable community case file
Equinix Profile Park Plot 100
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Permitted, recorded 19 February 2025 | Inspect the stage source and limits |
| Where is the formal decision evidence? | 1 planning item recorded | Check the authority's complete file, reference and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 2 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Evidence carried into this printout
- Recorded stage. Permitted, dated 19 February 2025: stage source
- Decision evidence. PL06S.317936 (SD22A/0156): ten-year permission for modifications to the permitted data centre SD21A/0186, refused on appeal: Refused, 19 February 2025.
- Checked statement. An Coimisiun Pleanala refused the appeal for modifications to the permitted Plot 100 data centre on 19 February 2025. source
- Checked statement. The application was accompanied by a Natura Impact Statement and an environmental impact assessment report. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
4 of 13 facility fields recorded
2 separately recorded source statements. These are not included in the facility-field count.
4 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Owner
- Capacity (MW)
- Grid connection
- Cooling
- PUE
- Water use
- Chips
- Connectivity
- Certifications
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Equinix Profile Park Plot 100: capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/equinix-profile-park-plot-100
BibTeX
@misc{computefinder_data_centres_equinix_profile_park_plot_100,
title = {Equinix Profile Park Plot 100: capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0024}},
number = {cf-dc-0024},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0024. Permanent link: https://computefinder.net/entity/cf-dc-0024. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/equinix-profile-park-plot-100. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0024"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in Ireland
- Google Grange Castle DC3
- EdgeConneX DUB06, Ballymakaily, Lucan
- Vantage Dublin DUB1 (Profile Park)
- Vantage DUB11, Ballybane and Kilbride, Clondalkin
- Cruiserath Road data centre expansion
All detailed records in Ireland / Same recorded stage in Ireland
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact