Data centres / UK and Ireland / Ireland
Pure DC Dublin Ballycoolin (DUB01 to DUB03)
Ballycoolin, Dublin 15, Ireland.
OperatingIreland
What we checked
- Pure DC says the Dublin campus has been operational since 2024 and comprises three data centres, DUB01, DUB02 and DUB03. (source)
- The operator says it bought a further 25 acres in 2023 to the west for future expansion. (source)
- A 21 July 2026 release says the Dublin campus is designed for up to 150MW of IT capacity, with 54MW currently permitted. (source)
A July 2026 release says the campus is designed for up to 150MW of IT capacity with 54MW currently permitted; the operator page also gives 54MW across three buildings and says it has been operational since 2024. Planning register entries were not fetched.
Operate this site or have better evidence? .
- Operator
- Pure DC
- Owner
- Not stated
- Stage
- Operating (source, 2 October 2026)
- Power
- Pure DC says the site self-generates with on-site dual-fuel gas generators backed by a 200MW thermal gas connection, and uses HVO for backup.
- Connectivity
- The operator describes the site as being in the fibre-rich Ballycoolin area.
Capacity
| Measure | Stage | Basis | MW | As of | Source |
|---|---|---|---|---|---|
| IT load | Permitted | permitted | 54 | 21 July 2026 | source |
These figures measure different things and are not added together.
Printable community case file
Pure DC Dublin Ballycoolin (DUB01 to DUB03)
Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.
Use this record as a shared case file
This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.
| Question | What this record currently shows | Useful next step |
|---|---|---|
| What stage is evidenced? | Operating, recorded 2 October 2026 | Inspect the stage source and limits |
| Where is the formal decision evidence? | Not recorded here. | First identify whether an application exists and which authority or process applies; then inspect its file, reference, status, consultation window, decision and conditions |
| How can the public participate? | Not recorded here. | Record the official route, deadline, decision-maker and how responses are considered |
| Which promises became outcomes? | Review 3 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome. | Keep proposed, committed and delivered states separate, with dates and responsible parties |
Evidence carried into this printout
- Recorded stage. Operating, dated 2 October 2026: stage source
- Checked statement. Pure DC says the Dublin campus has been operational since 2024 and comprises three data centres, DUB01, DUB02 and DUB03. source
- Checked statement. The operator says it bought a further 25 acres in 2023 to the west for future expansion. source
- Checked statement. A 21 July 2026 release says the Dublin campus is designed for up to 150MW of IT capacity, with 54MW currently permitted. source
Named next steps
Next decision and owner:
Participation route and deadline:
Evidence still required:
Review date:
This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.
What we do not know yet
These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.
5 of 13 facility fields recorded
3 separately recorded source statements. These are not included in the facility-field count.
5 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:
- Owner
- Grid connection
- Cooling
- PUE
- Water use
- Chips
- Certifications
- Planning reference
Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.
Cite this page
ComputeFinder. (2026, October 2). Pure DC Dublin Ballycoolin (DUB01 to DUB03): capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/pure-dc-dublin-ballycoolin
BibTeX
@misc{computefinder_data_centres_pure_dc_dublin_ballycoolin,
title = {Pure DC Dublin Ballycoolin (DUB01 to DUB03): capacity, planning and power},
author = {{ComputeFinder}},
year = {2026},
howpublished = {\url{https://computefinder.net/entity/cf-dc-0030}},
number = {cf-dc-0030},
note = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}Stable ID: cf-dc-0030. Permanent link: https://computefinder.net/entity/cf-dc-0030. It keeps working if this page moves.
Page link: https://computefinder.net/data-centres/pure-dc-dublin-ballycoolin. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.
Share this record
Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.
Embed code
<a href="https://computefinder.net/entity/cf-dc-0030"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>Other sites in Ireland
- Google Grange Castle DC3
- EdgeConneX DUB06, Ballymakaily, Lucan
- Equinix Profile Park Plot 100
- Vantage Dublin DUB1 (Profile Park)
- Vantage DUB11, Ballybane and Kilbride, Clondalkin
All detailed records in Ireland / Same recorded stage in Ireland
How we label evidence
- Official source the body that made the rule or the data says so
- Two sources agree independent sources match
- One source, not confirmed a single report or claim
- Watching a signal, not shown as a fact