Data centres / UK and Ireland / Ireland

Pure DC Dublin Ballycoolin (DUB01 to DUB03)

Ballycoolin, Dublin 15, Ireland.

OperatingIreland

What we checked

A July 2026 release says the campus is designed for up to 150MW of IT capacity with 54MW currently permitted; the operator page also gives 54MW across three buildings and says it has been operational since 2024. Planning register entries were not fetched.

Operate this site or have better evidence? .

Operator
Pure DC
Owner
Not stated
Stage
Operating (source, 2 October 2026)
Power
Pure DC says the site self-generates with on-site dual-fuel gas generators backed by a 200MW thermal gas connection, and uses HVO for backup.
Connectivity
The operator describes the site as being in the fibre-rich Ballycoolin area.

Capacity

Capacity
MeasureStageBasisMWAs ofSource
IT loadPermittedpermitted5421 July 2026source

These figures measure different things and are not added together.

Printable community case file

Pure DC Dublin Ballycoolin (DUB01 to DUB03)

Record checked 2 October 2026. Prepared from the public ComputeFinder record; follow each cited source before relying on it.

Use this record as a shared case file

This step helps residents, councils and builders move from a project record to the next checkable question. It does not establish local support, opposition, permission beyond the cited decision, or a delivered benefit.

Use this record as a shared case file
QuestionWhat this record currently showsUseful next step
What stage is evidenced?Operating, recorded 2 October 2026Inspect the stage source and limits
Where is the formal decision evidence?Not recorded here. First identify whether an application exists and which authority or process applies; then inspect its file, reference, status, consultation window, decision and conditions
How can the public participate?Not recorded here. Record the official route, deadline, decision-maker and how responses are considered
Which promises became outcomes?Review 3 checked statements and mark each as proposal, commitment, permission, construction, operation or delivered outcome.Keep proposed, committed and delivered states separate, with dates and responsible parties

Evidence carried into this printout

  • Recorded stage. Operating, dated 2 October 2026: stage source
  • Checked statement. Pure DC says the Dublin campus has been operational since 2024 and comprises three data centres, DUB01, DUB02 and DUB03. source
  • Checked statement. The operator says it bought a further 25 acres in 2023 to the west for future expansion. source
  • Checked statement. A 21 July 2026 release says the Dublin campus is designed for up to 150MW of IT capacity, with 54MW currently permitted. source

Named next steps

Next decision and owner:

Participation route and deadline:

Evidence still required:

Review date:

Open the community questions guide

Permanent case-file link

This is a route into the existing public evidence, not a verified local case study or a substitute for the formal planning file.

What we do not know yet

These facility fields are not recorded here. This does not show that the facility lacks them or that no source exists. A gap means unknown, never zero.

5 of 13 facility fields recorded

3 separately recorded source statements. These are not included in the facility-field count.

5 of 13 facility fields recorded against the existing target. Separately recorded source statements are not counted in this field measure. Still missing:

Checked on 2 October 2026. Reported and planned figures are shown as such. Not yet reviewed line by line by a second person. If something is wrong or you know more, tell us.

Cite this page

ComputeFinder. (2026, October 2). Pure DC Dublin Ballycoolin (DUB01 to DUB03): capacity, planning and power. ComputeFinder. Retrieved November 20, 2026, from https://computefinder.net/data-centres/pure-dc-dublin-ballycoolin

BibTeX
@misc{computefinder_data_centres_pure_dc_dublin_ballycoolin,
  title        = {Pure DC Dublin Ballycoolin (DUB01 to DUB03): capacity, planning and power},
  author       = {{ComputeFinder}},
  year         = {2026},
  howpublished = {\url{https://computefinder.net/entity/cf-dc-0030}},
  number       = {cf-dc-0030},
  note         = {Page last checked 2 October 2026. Retrieved 20 November 2026.}
}

Stable ID: cf-dc-0030. Permanent link: https://computefinder.net/entity/cf-dc-0030. It keeps working if this page moves.

Page link: https://computefinder.net/data-centres/pure-dc-dublin-ballycoolin. Page last checked 2 October 2026. Retrieved 20 November 2026. Cite the provider or the primary source for any fact you rely on.

Share this record

Link to this stable record with a neutral badge. It means the record is listed, not endorsed or ranked.

Listed on ComputeFinder

Embed code
<a href="https://computefinder.net/entity/cf-dc-0030"><img src="https://computefinder.net/listed-on-computefinder.svg" width="210" height="36" alt="Listed on ComputeFinder"></a>

Other sites in Ireland

All detailed records in Ireland / Same recorded stage in Ireland

How we label evidence
  • Official source the body that made the rule or the data says so
  • Two sources agree independent sources match
  • One source, not confirmed a single report or claim
  • Watching a signal, not shown as a fact